Product and project management · Beginner · 15 min
Plan and track work with GitHub Projects
By Padding · Updated 18 Nov 2026
GitHub (web) · November 2026
You will set up a GitHub project for a team repository with table, board and roadmap views, planning fields, automatic status updates, an issue form and an epic broken into sub-issues, plus a saved view for stakeholders.
On this page
If your team's code already lives on GitHub, you may not need a second tool to plan the work. GitHub Projects sits on top of the issues and pull requests you already have. A card on the board is the issue itself, so when a developer merges the pull request that fixes it, the plan updates without anyone copying a status from one system to another.
This tutorial follows Larkfield Clinic, the fictional community clinic from earlier tutorials, whose small team is adding online booking and appointment reminders. Their code is in a repository called booking, owned by the organisation larkfield-clinic. You build the project they plan in: three views over the same issues, the fields they plan with, the automations that keep status honest, an issue form so new work arrives in the same shape, and one epic broken into sub-issues. You finish with a saved view you can send to the clinic manager instead of writing a status email from scratch.
Use your own organisation, repository and work in place of Larkfield's as you go. Everything here happens in the GitHub web interface; there is nothing to install.
Step 1 · Create the project and link it to the repository
Create the project at organisation level, not on your personal account, so it survives if you leave the team and other people can manage it.
- Open your organisation's page on GitHub and click Projects, then New project.
- Under "Start from scratch", choose Table. You add the board and roadmap as extra views later; starting from a table makes the fields easier to set up.
- Name it after the outcome, not the tool. Larkfield's is "Booking and reminders".
- Tick Import items from repository and choose the repository (
booking). This brings in its existing issues and pull requests and makes it the project's default repository. - Click Create project.
Then go to the repository's home page, open its Projects tab, click Link a project and pick the project. Only projects owned by the same organisation as the repository appear in that list. Linking means anyone browsing the repository can find the plan from the code.
The address bar now shows something like github.com/orgs/larkfield-clinic/projects/1. Write down the number at the end; the issue form in a later step needs it.
Check it worked
The project opens as a table with one row for each issue and pull request imported from the repository (closed ones may appear too, so extra pull request rows are expected). On the repository's Projects tab, "Booking and reminders" is listed. If the table is empty, the repository had no issues yet: open two or three real ones now (for Larkfield, "Patients can pick a free slot online" and "Receptionist sees new online bookings") and confirm they appear in the table.
Step 2 · Add the fields the team plans with
A new project already has a Status field, with the options Todo, In Progress and Done. Add three more. In the table, click the + at the right end of the column headers, then New field, type the name and choose the type.
- Priority, single select: Urgent, High, Normal, Low. Four is enough. If everything is Urgent, the field stops telling you anything.
- Size, single select: S, M, L. Larkfield defines them in the option descriptions: S is under a day, M is two or three days, L is about a week. Anything bigger is an epic and gets split (see the sub-issues step).
- Iteration, iteration type: set the duration to 2 weeks and the start date to the Monday your next cycle begins. GitHub creates three iterations ahead. If the team has a known gap, such as a public holiday week, open the project Settings, choose the iteration field and use Insert break so the gap does not count as a sprint.
Status options can be changed too. Larkfield added In review between In Progress and Done, because pull requests waiting for a reviewer were hiding inside In Progress. Click the Status column header, then the field's settings, to add or reorder options.
Now fill the fields for every row. Click a cell and choose a value; you can paste a value down a column to set several rows at once.
Check it worked
Your table has columns for Title, Status, Priority, Size and Iteration, and no row has an empty Priority or Size. Type no:priority in the filter bar: the table should show no items. Clear the filter afterwards.
Step 3 · Build the table, board and roadmap views
Each tab across the top of a project is a view: the same items with a different layout, filter, grouping and sort. Set up three, then save each one so the whole team sees the same thing.
Backlog (table). Rename the first view: open View options (the small menu on the view's tab), choose Rename view, and call it "Backlog". Sort by Priority, then group by Iteration so unscheduled work collects under "No Iteration" at the bottom. When you change a view, a dot appears next to its name; open View options and click Save changes, or the change stays on your screen only.
This iteration (board). Click New view, switch the layout to Board and rename it "This iteration". The board makes one column per Status option. Type iteration:@current in the filter bar so it shows only the current two weeks, then save. This is the view the team opens at stand-up.
Plan (roadmap). Click New view, switch to Roadmap and rename it "Plan". Open the Date fields menu and choose Iteration for both the start and the target, so each item sits across the iteration it belongs to. Set the zoom to Quarter and save.
Keep the number of views small. Three that everyone uses beat eight that each belong to one person.
Check it worked
The project has three tabs, Backlog, This iteration and Plan, and none of them shows the unsaved-changes dot. On the board, drag one card from Todo to In Progress, then switch to the Backlog table: the same item's Status reads In Progress. One item, three views.
Step 4 · Let the built-in workflows move cards for you
Status that depends on people remembering to drag cards drifts within a week. Projects has built-in workflows that change fields when something happens to an issue or pull request.
Open the project's menu (the ... at the top right) and choose Workflows. Two are on by default in a new project:
- Item closed sets Status to Done when an issue or pull request in the project is closed.
- Pull request merged sets Status to Done when a pull request in the project is merged.
Click each one to confirm it is on and that it sets Status to Done (or your own final option if you renamed it). If you edit one, finish with Save and turn on workflow. Read through the rest of the list too; there are workflows for other events, and you can turn on any that match how your team works.
Then set up Auto-add to project, so new issues land in the project without anyone adding them. Click it, click Edit, choose the booking repository under "Filters" and enter is:issue is:open, then Save and turn on workflow. Two things to know: it only adds items created or updated after you turn it on, so older issues still need adding by hand, and the number of auto-add workflows depends on your plan (GitHub Free allows one, so point it at your main repository).
The habit that makes this pay off is linking pull requests to issues. When a developer writes Closes #42 in a pull request description, merging the pull request closes issue 42, and the Item closed workflow moves its card. Ask the team to do this on every pull request.
Check it worked
Pick an issue on the This iteration board, open it and click Close issue. Go back to the board without touching the card: it is now in the Done column. Reopen the issue if it was not really finished. Then open a new test issue in the repository and confirm it appears in the Backlog table within a minute or so; close it as not planned when you have seen it arrive.
Step 5 · Add an issue form so new work arrives complete
Half-written issues ("booking broken??") cost a planning meeting ten minutes each. An issue form asks the reporter the questions you would ask, and can add the issue to the project as it is created.
In the repository, create the file .github/ISSUE_TEMPLATE/feature-request.yml. You can do this in the browser: Add file, Create new file, type the path, paste the content and commit it to the default branch.
name: Feature request
description: Ask for a change to online booking or reminders.
title: "[Request]: "
labels: ["request"]
projects: ["larkfield-clinic/1"]
body:
- type: textarea
id: who-and-why
attributes:
label: Who needs this and why?
description: Name the person (patient, receptionist, nurse) and the problem they have today.
placeholder: Receptionists retype every online booking into the diary because...
validations:
required: true
- type: textarea
id: done-looks-like
attributes:
label: How will we know it is done?
description: One or two checks someone could do on the live site.
validations:
required: true
- type: dropdown
id: deadline
attributes:
label: Is there a fixed date?
options:
- No fixed date
- Yes, there is a fixed date
validations:
required: true
- type: input
id: deadline-date
attributes:
label: If yes, what is the date and why?
placeholder: 31 March, when the new clinic opensReplace larkfield-clinic/1 with your organisation name and the project number you wrote down. The projects line only works for people who have write access to the project; if requests come from people outside the team, the auto-add workflow from the last step catches their issues instead. Labels must already exist in the repository, so create a request label first (Issues, Labels, New label) or remove that line.
For writing the questions themselves, the tutorial on tickets developers want to pick up covers what a good ticket contains.
Check it worked
In the repository, click Issues, then New issue. "Feature request" appears in the template chooser with your description. Open it: the title starts with [Request]: ` and the form will not submit while a required box is empty. Submit one real request; it appears in your project's Backlog table with the `request label.
Step 6 · Break an epic into sub-issues
Larkfield's biggest piece of work is "Appointment reminders by SMS". It is far larger than an L, so it becomes a parent issue, and the pieces become sub-issues that each fit in an iteration.
- Open a new issue titled "Appointment reminders by SMS". In the description, write the outcome in two or three lines: patients get a text the day before their appointment, and fewer appointments are missed.
- At the bottom of the description, click Create sub-issue. Add each piece, ticking Create more sub-issues to keep going:
- Clinic can set how long before an appointment the reminder goes out
- Reminder text with the clinic name, date, time and a reply-to-cancel line
- Patients can opt out of reminders
- Send reminders for the next day's appointments every evening
- If a matching issue already exists, use the arrow next to Create sub-issue and choose Add existing issue instead of creating a duplicate.
A parent can hold up to 100 sub-issues, nested up to eight levels deep. One level is plenty for most teams; if you find yourself three levels down, the epic is probably two epics.
Give each sub-issue a Size and an Iteration in the project. For the parent, add a label epic (create it first if you need to). Then, in the Backlog view, click the + in the column headers and add the Sub-issue progress field, so every parent shows how many of its children are done.
Larkfield's clinic sees patients who speak several languages, so the reminder text sub-issue says which languages are needed and that the text must fit one SMS segment, since longer messages cost more to send and some patients read them on basic phones. Writing that constraint into the sub-issue now saves a rewrite later.
Check it worked
Open the parent issue: it lists four sub-issues with a progress count such as 0 of 4. In the Backlog table, the parent's Sub-issue progress cell shows the same count. Close one sub-issue; the count on the parent changes, and the closed sub-issue's card moves to Done on the board by itself.
Step 7 · Save a view for the stakeholder update
The clinic manager does not need to see every bug. She needs to know which big pieces are on track and what lands next. Build a view for her rather than writing that up by hand each week.
- In the Plan roadmap view, open View options and choose Duplicate view. Rename the copy "For clinic manager".
- Filter it to the epics that are still open:
label:epic is:open. - Turn on Markers for iterations so the timeline shows each two-week cycle.
- Keep Sub-issue progress visible so each epic shows how far through it is.
- Click Save changes.
Copy the browser address of this view; the link opens straight to it. Paste it at the top of your weekly update, under one or two lines of your own about risks or decisions you need. The view shows the plan; you still have to say what it means. The tutorial on writing a weekly stakeholder update covers that part.
Check who can open it before you send it. A private project is only visible to people with access, so either give the manager read access to the project or, if that is not possible, take a screenshot. A single page in a phone browser is a lighter download than a slide deck attachment, which helps if she reads updates on a prepaid mobile connection.
Check it worked
Open the link in a private browser window while signed in as someone with read access (or ask the manager to open it). It lands on "For clinic manager", shows only open epics, and the SMS reminders epic shows its progress count. Nothing on the screen needs explaining before she can tell what is planned for this iteration and the next.
Next steps
Run one full iteration in the project before changing anything. At the retrospective, look at which cards moved without anyone touching them and which were still wrong, and adjust the workflows or fields from what you saw.
- If the team is new to Git and pull requests, start with push to GitHub with SSH and open a pull request, so
Closes #42becomes a habit. - If people outside engineering need a planning tool of their own, compare this with setting up a Jira project for a small team or setting up Linear for a product team.
- Improve what goes into the backlog with tickets developers want to pick up.
Related tutorials
- Write user stories with clear acceptance criteriaYou will have five user stories for a clinic's reschedule feature, each checked against INVEST and carrying Given / When / Then acceptance criteria that a developer and a tester read the same way.
- Write tickets developers want to pick upYou will rewrite three vague backlog tickets into ones a developer can start without asking a question, and save the structure as a ticket template in your tracker.
- Write a weekly stakeholder update people readYou will have a reusable weekly update template and one finished update under 250 words, whose first two lines tell any reader whether they need to act.