Product and project management · Beginner · 12 min
Write a weekly stakeholder update people read
By Padding · Updated 18 Nov 2026
Email or any document editor · November 2026
You will have a reusable weekly update template and one finished update under 250 words, whose first two lines tell any reader whether they need to act.
On this page
Most weekly updates fail in the same way. They open with background, list every task the team touched, and hide the one thing the reader needed to know in the fourth paragraph. Busy people learn that the update rarely asks anything of them, so they stop opening it. Then the week something does go wrong, nobody reads it.
A good update reverses that. The first line says whether the project is on track and why. The second says whether the reader has to do anything, and by when. Everything after that is there for people who want more, and most of the detail sits behind links.
The running example is Larkfield Clinic, the fictional community clinic building online booking and SMS appointment reminders. You are its product lead. Every Friday you write to the practice manager and the clinic board. The project's state this week:
- GP online booking works end to end on the test site.
- The clinic is switching SMS providers because the old one is closing its service in the region.
- A new (fictional) regulator rule says every patient needs a recorded consent before the clinic sends any appointment message, with a fixed deadline of 1 March. Consent records are now the team's main piece of work.
- The new provider's contract is waiting for the practice manager's approval.
If you have your own project, use it. The steps are the same.
Step 1 · List your readers and what each one can act on
Before you write a word, list who receives the update and what each person can actually do with it. An update is a tool for getting the right decisions made at the right time, not a diary of the week.
Write one line per reader in your document: who they are, what they can decide or do, and what they care about most. For Larkfield:
- Practice manager: approves contracts and spending up to the clinic's limit, and can free up staff time. Cares about cost, staff time and patient complaints.
- Board chair and board: approve the budget and report to funders. Care about the 1 March deadline and the clinic's reputation.
- GP lead: agrees clinical wording and can recruit patients for testing. Cares about anything that changes clinic sessions.
If a reader cannot decide or do anything with the update, ask whether they need it every week. Some people are better served by a monthly summary or a link they can check when they want.
Check it worked
Your list names every person on the distribution list. Each one has at least one thing they can decide or do. Anyone without an entry has been moved to a less frequent summary, or has a reason written next to their name.
Step 2 · Agree what on track, at risk and off track mean
The status line only works if everyone reads the words the same way. Write the definitions once, put them at the bottom of the template, and use them every week:
- On track: we will meet every committed date without help from you.
- At risk: we may miss a committed date unless one specific thing happens. The update says what that thing is and who can make it happen.
- Off track: we will miss a committed date. The update gives the new forecast and the options.
Judge the status against commitments, not effort. A team working hard on the wrong things is not on track. Look at the dates in your plan, then at what has to be true to hit them.
Avoid two habits that destroy trust. The first is reporting "on track" until the week before a deadline and then jumping to "off track": if something could make you miss a date, that is "at risk", and saying so early gives people time to help. The second is using "at risk" every week as a hedge. If it is at risk for three weeks running with nothing changing, it is probably off track.
At Larkfield this week, the 1 March consent deadline is fixed by the regulator. Consent work cannot start testing until the new SMS provider is signed up, and the provider needs about two working weeks to approve the clinic's sender name. If the contract waits past 11 December, the March date gets tight. That is "at risk", with a clear thing that fixes it.
Check it worked
Your template has the three definitions written out. You can say which one applies to your project this week, and, if it is not "on track", you can name the single event or decision that would change it.
Step 3 · Write the first two lines
Write the status line and the action line before anything else. Together they should make sense to someone who reads nothing more.
The status line is the status word, then the reason in one sentence:
Status: At risk. Consent records may miss the fixed 1 March deadline because the new SMS provider contract is not signed yet.
The action line says who needs to do what, and by when. Name the person and give a day and a date:
Decision needed: Practice manager to approve the Provider B contract by Friday 11 December. Without it, consent testing slips into February.
When nobody needs to act, say that plainly: "No action needed from you this week." That line is useful in itself; it tells readers they can stop there.
Put the same two lines in the email subject, shortened: "Larkfield booking, w/e 4 Dec: At risk, contract decision by 11 Dec". People triage by subject line, so the subject should already say whether to open it now.
Write dates as words ("Friday 11 December"), not numbers. Readers in the UK, Nigeria, Kenya and the US do not all read 11/12 the same way, and a misread deadline is worse than none.
Check it worked
Cover everything below your first two lines and read them aloud. Someone who has not seen the project knows whether it is on track, why, and whether they personally have to do something before a named date.
Step 4 · Write what shipped and what is next
Below the first two lines, list what the team finished this week and what it will do next week. Two or three bullets each is plenty.
Write outcomes a reader can picture, not tasks. "Reception booked 40 practice appointments on the test site with no double bookings" tells the board something. "Finished the slot-locking ticket" does not.
For Larkfield:
Shipped this week- GP booking works end to end on the test site. Reception staff made 40 practice bookings with no double bookings.- Consent wording agreed with the GP lead (link). >Next week- Start the reception screen for recording consent (target: Friday 18 December).- Test the booking form on a low-cost Android phone over a slow connection.
Only include "next" items you are confident about. If the team does not finish one, it appears in next week's update as not done, with a reason. That keeps the list honest.
Check it worked
Each bullet describes something a non-technical reader could see or check. There are no more than three bullets under each heading, and every "next" item has a target date or week.
Step 5 · Add decisions, risks and asks
Now list what you need from people and what could go wrong. Keep them in three separate short sections so nothing important gets lost in a paragraph.
- Decisions needed: what to decide, who decides, by when, and a link to the options. Repeat the decision from your action line here with the link.
- Risks: what might happen, what it would affect, and what you are doing about it. Link to your risk register rather than copying it.
- Asks: smaller requests for help, each with a named person.
Put bad news here the first week you know it, even if you are not sure yet. "We may need to change SMS provider; we will know by Wednesday" is far easier for a board to hear than a surprise a fortnight later. When the risk turns out to be nothing, say so next week and remove it.
For Larkfield:
Decisions needed- Approve the Provider B contract. Practice manager, by Friday 11 December. Comparison of the shortlist (link). >Risks- Provider B needs about 10 working days to approve our sender name. A contract signed after 11 December pushes consent testing into February (risk register, link).- One developer is on leave 21 December to 4 January. The plan already allows for it. >Asks- GP lead: 30 minutes next week with three patients trying the booking form.
Check it worked
Every decision has an owner and a date. Every risk says what it would affect. Every ask names one person. Nothing in these sections is longer than two lines, and the detail lives behind links.
Step 6 · Cut it to 250 words and send it as plain text
Count the words. Most editors and email clients show a word count, or paste the text into any document that does. If you are over 250 words, cut in this order:
- Background the readers already know.
- Shipped items that no reader will act on or ask about.
- Explanation that belongs in a linked document.
Never cut the status line, the action line or a risk to save space.
Send the update in the body of the email or message, as plain text with bold headings, not as an attached PDF or slide deck. Many readers open it on a phone between other tasks. If some of your board read on low-cost Android phones or prepaid mobile data, as is common for community board members in Nigeria and across Africa, an attachment may cost money to open and often goes unread. Keep to three or four links, and point each one at a single page rather than a large shared folder.
Here is Larkfield's finished update. It is 230 words, including the subject line.
Subject: Larkfield booking, w/e 4 Dec: At risk, contract decision by 11 Dec >Status: At risk. Consent records may miss the fixed 1 March deadline because the new SMS provider contract is not signed yet. >Decision needed: Practice manager to approve the Provider B contract by Friday 11 December. Without it, consent testing slips into February. >Shipped this week- GP booking works end to end on the test site. Reception staff made 40 practice bookings with no double bookings.- Consent wording agreed with the GP lead (link). >Next week- Start the reception screen for recording consent (target: Friday 18 December).- Test the booking form on a low-cost Android phone over a slow connection. >Decisions needed- Approve the Provider B contract. Practice manager, by Friday 11 December. Comparison of the shortlist (link). >Risks- Provider B needs about 10 working days to approve our sender name. A contract signed after 11 December pushes consent testing into February (risk register, link).- One developer is on leave 21 December to 4 January. The plan already allows for it. >Asks- GP lead: 30 minutes next week with three patients trying the booking form. >Changed since last week: status moved from on track to at risk because of the provider contract. >Plan and roadmap (link). Questions: reply to this email, or find me at reception on Monday morning.
Check it worked
Your update is under 250 words, sits in the body of the message, and has no attachments. Every link opens one specific page. The "Changed since last week" line tells a regular reader what is different without them comparing two emails.
Step 7 · Tailor the top for an executive or a clinician
Keep one set of facts and one structure for everyone. What changes between readers is the first two lines and which section you lead with, because different people act on different things.
An executive or board member wants the commitment, the risk to it, and the decision. The Larkfield version above is already written for them.
A clinician wants to know whether anything changes in their sessions and whether you need their time. For the GP lead, Larkfield's update starts:
Status: At risk. Nothing changes in clinic this week. The risk is a contract delay, which the practice manager is handling. >Ask: 30 minutes of your time next week to watch three patients try the booking form. Any day suits; tell me which.
The rest of the update stays the same. If you find yourself writing different facts for different readers, stop: people compare notes, and two versions of the truth cost more trust than any delay. If your readers work in more than one language, keep the status word and the dates the same in every version, so they can be matched at a glance.
If one group needs a very different level of detail every week, send them a separate short note that links to the main update, rather than a second full update.
Check it worked
Put your executive and clinician versions side by side. The status word, dates, risks and decisions match exactly. Only the first two lines and the order of the sections differ, and each version's second line is something that reader can act on.
Step 8 · Save the template and fix the day you send it
Turn this week's update into a template so next week takes 20 minutes, not an hour. Save it as a draft email or a document called "Weekly update template" with the headings and the prompts that remind you what goes under each:
Subject: [Project], w/e [date]: [Status], [action and date, or "no action needed"] >Status: [On track / At risk / Off track]. [Reason in one sentence.] >Decision needed: [Who] to [do what] by [day and date]. Or: No action needed from you this week. >Shipped this week (up to 3 outcomes a reader can picture) >Next week (up to 3, each with a target date) >Decisions needed (what, who, by when, link to options) >Risks (what might happen, what it affects, what you are doing, link) >Asks (one named person each) >Changed since last week: [one line] >Plan and roadmap (link). >Status meanings: On track: we will meet every committed date without help. At risk: we may miss a committed date unless one specific thing happens. Off track: we will miss a committed date; new forecast and options below.
Pick a day and time and keep to it, for example Friday by 3pm. Readers learn when to expect it. A missing update makes people assume bad news, so if there is truly nothing to report, send the template with "On track. No action needed from you this week" and one line on what happened.
Use the same format even in a crisis. When the news is bad, a familiar layout helps people find the decision quickly instead of reading a long, unusual email for clues.
Check it worked
You have a saved template with every heading, the prompts and the status definitions. A recurring reminder is in your calendar for the send day. Open the template and fill in the first two lines for next week from memory: if you can, the format is working.
Next steps
You now have a template, one finished update under 250 words, and a fixed day to send it. After four weeks, ask two readers whether they read past the first two lines and whether anything was missing. Change one thing at a time.
- When the plan itself has to change, run the review in keep a roadmap honest when plans change and send the result in this format.
- Give your risks section something solid to link to with keep a risk register for your project.
- Base your "on track" calls on evidence with forecast delivery dates from throughput.
- Use the same lead-with-the-action approach for research in report research findings so the team acts.
Related tutorials
- Write user stories with clear acceptance criteriaYou will have five user stories for a clinic's reschedule feature, each checked against INVEST and carrying Given / When / Then acceptance criteria that a developer and a tester read the same way.
- Write tickets developers want to pick upYou will rewrite three vague backlog tickets into ones a developer can start without asking a question, and save the structure as a ticket template in your tracker.
- Write a product requirements document engineers actually useYou will have a short, living PRD for Larkfield Clinic's SMS appointment reminders, with testable requirements, edge cases, limits, analytics events, owned open questions and a change log, that links to designs and tickets instead of copying them.
Need this done for you?
Padding does this work for growing companies, from the first diagnosis to a system that keeps working.
Get new tutorials