Keep a roadmap honest when plans change

By Padding · Updated 18 Nov 2026
Any document editor · November 2026

You will run a monthly roadmap review that ends with a revised roadmap, a change log giving a dated reason for every moved or retired item, and the message you send stakeholders before they hear the news elsewhere.

On this page

A roadmap is only useful while people believe it. Every plan goes wrong at some point, and that does not damage trust. What damages it is a roadmap that keeps showing the old plan after everyone in the room knows it is dead, or one that changes without a word, so a board member finds out from a receptionist that the thing they were promised has gone.

This tutorial is about the review that keeps a roadmap believable: a short, regular meeting with yourself and your team where you compare the plan with what happened, move what has to move, drop what the evidence no longer supports, and tell people. If you have not built a roadmap yet, start with build a now, next, later roadmap around outcomes and come back.

The running example is the Larkfield Clinic roadmap from that tutorial, a fictional community clinic moving to online booking and appointment reminders. The board saw it on 18 November 2026, with the next review set for 16 December 2026. It held problems and outcomes, not features:

  • Now: patients forget appointments (owner: product lead; current bet: a 12-week SMS reminder trial from 6 January); booking records sit on an unsupported server (owner: practice manager; FIXED 28 Feb 2027, support contract ends).
  • Next: patients can only book by phone; cancelling means a phone call (FIXED 1 Jul 2027, health board rule); new patients wait to register.
  • Later: reminders only in English; carers book by phone; repeat prescriptions tie up the phone lines.

In the four weeks since, three things have happened, all fictional:

  • 2 December 2026: the SMS provider wrote to say it is closing its service in the region on 31 December 2026, one week before the trial was due to start.
  • 9 December 2026: the regional health board published a rule that clinics must hold a recorded consent for every patient before sending them any appointment message, from 1 March 2027.
  • 25 November 2026: the health board announced that its regional pharmacy app will take repeat prescription requests for every clinic in the region from April 2027.

It is now 16 December 2026, the day of the scheduled review. Use your own roadmap if you have one. The steps are the same.

Step 1 · Put the plan and the reality side by side

Open a blank document and title it with the roadmap's name and today's date, for example "Larkfield roadmap review, 16 December 2026". Make a table with five columns:

  • Item: each item exactly as it appears on the current roadmap.
  • Column then: where it sat at the last review (now, next or later).
  • What we said: the promise in the words people heard, including any date.
  • What happened: what shipped, what is in progress, and what has not started.
  • What changed outside: anything new that affects the item, such as a supplier, a rule, a cost or a finding from research.

Fill it in from records, not memory. Use your issue tracker, release notes, the last update you sent, board minutes and the roadmap itself. For "What we said", find the actual sentence. People remember what they were told, so you need to know exactly what that was.

For Larkfield, three of the eight rows look like this:

Item: Patients forget appointments. Column then: now. What we said: "Current bet: 12-week SMS reminder trial from 6 January" (roadmap, 18 November 2026); the board minutes record the chair saying "reminders start in January". What happened: message templates written and tested; sending code 70 per cent done against the old provider's interface. What changed outside: provider closing 31 December 2026 (notice, 2 December); consent rule from 1 March 2027 (health board, 9 December).
Item: Booking records sit on an unsupported server. Column then: now. What we said: "FIXED 28 Feb 2027 · support contract ends" (roadmap). What happened: 60 per cent of records moved and checked. What changed outside: none.
Item: Repeat prescriptions tie up the phone lines. Column then: later. What we said: shown in Later, no date (roadmap). What happened: nothing started. What changed outside: the health board's pharmacy app will take repeat prescription requests for every clinic in the region from April 2027 (announcement, 25 November).

The other five rows (online booking, cancelling, registration, reminders in other languages, carers) have "nothing started" and "none" in the last two columns.

Do not judge anything yet. This step is only about getting the facts on one page.

Check it worked

Every item on the current roadmap has a row. Every "What we said" cell quotes or closely paraphrases a real source and names it. If you cannot find where a promise was made, write "not found" rather than guessing, because that gap matters later when you decide who to tell.

Step 2 · Give every item one of four decisions

Add a sixth column, Decision, and give each row exactly one of these:

  • Keep: it stays where it is, and the promise still holds.
  • Move: it changes column, changes its current bet or changes scope.
  • Retire: it comes off the roadmap, because the evidence no longer supports doing it.
  • Add: a new item the changes outside have made necessary. Add a row for it.

Then add a seventh column, Why, and write one sentence for every decision except a plain keep. The sentence must point to something a sceptic could check: a date, a letter, a number, a published notice. "Priorities changed" is not a reason. "The provider's closure notice of 2 December 2026 means we cannot send through it after 31 December 2026" is.

Larkfield's decisions:

  • Patients forget appointments: move, by changing the bet. The problem and its outcome (missed-appointment rate, 7.2% to below 5%) stay in Now. The bet changes from "12-week SMS reminder trial from 6 January" to "switch to a new SMS provider and run the 12-week trial only with patients who have recorded consent". Why: the provider closes on 31 December 2026 (notice, 2 December), and a trial starting 6 January would run past 1 March 2027, when the health board's consent rule (9 December) would stop it halfway.
  • The clinic cannot message patients without recorded consent: add, in Now. Outcome: share of patients with a mobile number who have recorded consent. Why: the health board's rule requires it from 1 March 2027, and the reminder trial cannot start without it.
  • Booking records sit on an unsupported server: keep. On track at 60 per cent moved.
  • Cancelling means a phone call: keep, in Next. Its fixed date (1 July 2027) is untouched, and there is still time to do the work if it starts in March.
  • Repeat prescriptions tie up the phone lines: retire. Why: the health board's pharmacy app will take repeat prescription requests for every clinic in the region from April 2027 (announcement, 25 November), so building Larkfield's own would duplicate it. The outcome is still worth watching: if prescription calls per week do not fall after April, the problem can come back.
  • Everything else: keep.

Retiring is the hardest decision to make, because somebody usually asked for the item. Do it anyway when the evidence says so. A roadmap that only ever grows stops meaning anything.

Check it worked

Every row has one decision, and the new consent item has a row of its own. Every move, retire and add has a sentence in Why that names a document, a date or a number, and each of those sources appears in the "What changed outside" column from the step before. Read each reason as if you were the person who asked for that item: would you accept it, or would you ask "says who?"

Step 3 · Check the dates on everything that moved

The roadmap tutorial tested every date with one question: "What happens, and to whom, if we miss it?" A date with a consequence outside the team is FIXED and goes on the roadmap as a tag; any other date is a target and stays off it. See mark the dates that are real commitments for the full test. In a review, apply it again to every item you moved or added, and add a column, Kind of date.

At Larkfield:

  • 1 March 2027, consent records: fixed. The health board set it, and after that date the clinic cannot send any appointment message without consent. It goes on the new item as "FIXED 1 Mar 2027 · health board consent rule".
  • 6 January, start of the SMS trial: a target. It slipped onto the roadmap inside the wording of the bet, and the board heard it as a promise. The new target, April 2027, goes in the change log and the stakeholder message, not on the roadmap, so the same mistake does not happen twice.
  • 28 February 2027 and 1 July 2027: fixed and unaffected, but check each still has enough time left now that the team has more in Now.

Fixed dates get protected: when you are short of time, target items move so that fixed ones do not. Moving a fixed date is a different conversation, usually an escalation to whoever owns the risk, covered in keep a risk register for your project.

Be honest about targets that you allowed to sound fixed. The board heard "January", so treat the message about it with the same care as a broken commitment, even if it was only ever a plan.

Check it worked

Every moved or added item with a date is marked fixed or target, and each fixed date names its outside source (for Larkfield: "health board rule, published 9 December 2026"). No target date has been written onto the roadmap, and no fixed date has been moved without a note that it needs escalating.

Step 4 · Write the change log

The table you have built is your working document. The change log is the short, permanent record that sits next to the roadmap so anyone can see how it got to where it is. Start a section at the bottom of the roadmap, or a separate page linked from it, called Change log. Add the newest entry at the top.

Each entry has the same five parts:

  • Date: the day of the review.
  • Item: the item's name as it appears on the roadmap.
  • Change: from what to what, in one line.
  • Reason: the sentence from your Why column, with a link to the evidence.
  • Decided by: the person or group who made the call.

Larkfield's entry for the reminders:

16 December 2026 · Patients forget appointmentsChange: current bet from "12-week SMS reminder trial from 6 January" to "new SMS provider; 12-week trial with patients who have recorded consent". Trial start is now targeted for April 2027 (target, not shown on the roadmap).Reason: SMS provider closing its service on 31 December 2026 (closure notice, 2 December, linked). The health board's consent rule applies from 1 March 2027 (rule, 9 December, linked), so we will record consent first and run the trial on top of it.Decided by: product lead, with the clinic manager.

Write the repeat prescriptions entry just as carefully, and say plainly that the item is gone and why, with a link to the health board's announcement. People who asked for it should be able to find out what happened without having to ask you.

Never edit or delete an old entry. If a later review reverses a decision, add a new entry that says so. The log is useful because it shows the path, including the wrong turns.

Check it worked

Every item you marked move, retire or add has a change log entry with a date, a reason and a named decider. Every reason links to, or names, the evidence behind it. Read the log from the top: someone who missed the last two months should be able to tell what changed and why without opening anything else.

Step 5 · Redraw the roadmap

Now update the roadmap itself. Make the changes from your decision column and nothing else, so the roadmap and the log agree.

For Larkfield, the revised roadmap reads:

  • Now: patients forget appointments (product lead; current bet: new SMS provider, 12-week trial with patients who have consented); the clinic cannot message patients without recorded consent (reception lead; current bet: ask at check-in and on every booking call; FIXED 1 Mar 2027 · health board consent rule); booking records sit on an unsupported server (practice manager; FIXED 28 Feb 2027 · support contract ends).
  • Next: patients can only book by phone; cancelling means a phone call (FIXED 1 Jul 2027 · health board rule); new patients wait to register.
  • Later: reminders only in English; carers book by phone.

Two small additions help people trust the new version:

  • A line at the top saying "Last reviewed 16 December 2026. See change log for what changed." This tells readers the roadmap is alive.
  • A short marker beside each item that changed in this review, such as "changed 16 Dec", removed at the next review.

Keep the rule from the original roadmap: only FIXED items carry a date. If your own roadmap already shows target dates, label each one "target" in the item so nobody reads it as a commitment, and consider moving them into the change log at this review.

Check how much is now in Now. Larkfield planned for two items at a time and now has three, and none can move out: two have fixed dates and the third is the clinic's main outcome. If your Now column has grown, either move something else out or write down, in the change log, why the team can absorb the extra work. Larkfield's reason: most of the consent work is reception asking patients, and the developer time freed by pausing the SMS sending code covers the small consent form. A longer Now column with no explanation is how a roadmap stops being honest again a month later. Forecast delivery dates from throughput shows how to check whether the April target is realistic.

Check it worked

Every change on the roadmap has a matching change log entry, and every change log entry from today shows up on the roadmap. The "last reviewed" line has today's date. The only dates on the roadmap are FIXED tags. If Now holds more items than before, the change log says why that is workable.

Step 6 · Tell the people most affected before anyone else

Before you send anything to the whole group, list the people who were promised something that has now moved or gone, or who are being asked to take something new on. Your "What we said" column tells you who they are. For each one, note what they were told, what has changed and what it means for them.

At Larkfield, the list has three people:

  • The clinic board chair, who told the clinic's funders that reminders start in January.
  • The reception lead, who has been telling patients that text reminders are coming in January, and who now owns the consent item.
  • The GP who asked for online repeat prescriptions when the roadmap was first built.

Talk to each of them before the group message goes out, ideally in person or on a call, and keep it short: what changed, why, what happens now, and what you need from them. For the board chair, that includes giving them the words to use with the funders. For the reception lead, it means a new line to use with patients ("text reminders are coming in the spring, and we need your permission first") and agreeing how consent will be asked. For the GP, it means showing the health board's announcement and asking whether the pharmacy app will work for their patients, or whether there is a gap you have missed.

This is the part of roadmap work that is about relationships more than plans. People can accept a slipped date. What they struggle to accept is being embarrassed in front of someone else because they were the last to know. If someone pushes back with evidence you did not have, change your decision and log it. If they push back without evidence, listen, note it, and keep the decision.

Check it worked

You have a list of everyone who was promised something that moved or was retired, and everyone given new work. Each name has a date beside it showing when you spoke to them, and that date is before you sent the group message. Any new evidence from those conversations is either reflected in the change log or noted as considered and not acted on.

Step 7 · Send the change message

Now write the message to everyone who follows the roadmap. Keep it short enough to read on a phone, and put the news first. A structure that works:

  1. One line on what changed most. Lead with the biggest change, not with background.
  2. Why, in two or three sentences. Use the reasons from the change log.
  3. What happens now. The new dates, each labelled fixed or target.
  4. What else changed. One line per item, with a link to the change log for detail.
  5. What you need. Any decision or help you are asking for, with a date.

The message is where a target date belongs, because readers need it to plan, and the label tells them how much weight it carries. Larkfield's message to the board, practice staff and the development team:

Subject: Roadmap update: SMS reminder trial now April 2027, consent records first >The SMS reminder trial will now start in April 2027, not January. >Our SMS provider is closing its service on 31 December, so we have to switch to a new one. The health board also now requires recorded patient consent before any appointment message, from 1 March 2027. Recording consent first, then running the trial, avoids a trial that would have to stop halfway. >Now: consent records must be in place by 1 March 2027 (fixed). The reminder trial with patients who have consented is targeted for April 2027 (target). The move off the old booking server is on track for 28 February 2027 (fixed). >Also changed: online repeat prescriptions are retired, because the health board's pharmacy app will take these requests from April 2027. Full details are in the change log (link). >What I need: the clinic manager to approve the new SMS provider shortlist by 23 December 2026.

Send it from the same place, in the same format, as your regular updates, so it does not look like a crisis. If you already send a weekly update, use it, as described in write a weekly stakeholder update people read.

If some of your readers use low-cost Android phones or prepaid mobile data, as many clinic staff and community board members across Africa and elsewhere do, send the message as plain text in the email or chat body rather than as an attached slide deck or PDF. A link to the full roadmap is fine; a large attachment that costs data to open often goes unread.

Check it worked

The first line of your message tells a reader the biggest change without them reading on. Every date in it says whether it is fixed or a target. Every moved or retired item is either named or covered by the link to the change log. The message ends with a specific request, a person and a date, or says plainly that nothing is needed.

Step 8 · Set the next review and the triggers that bring it forward

Finish by deciding when you will do this again. A monthly review suits most small teams: often enough that nothing drifts for long, not so often that the roadmap churns. Larkfield's next one is 13 January 2027. Put yours in the calendar now.

Then write down, at the top of the change log, two or three triggers that mean you review straight away instead of waiting:

  • A fixed date comes under threat.
  • A supplier, partner or rule changes in a way that affects an item in Now.
  • Research or data contradicts the reason an item is on the roadmap.

At Larkfield, the second trigger would have brought this review forward by two weeks, from 16 December to 2 December, the day the closure notice arrived. That would have given the board chair two more weeks to prepare the funders. Next time, the product lead reviews the day a trigger fires.

Check it worked

The next review is in your calendar with a date within the next five weeks. The change log starts with a short list of triggers, and each trigger is specific enough that you would know when it has happened.

Next steps

You now have a revised roadmap, a change log with a dated reason for every moved or retired item, and the message you sent. Keep the review document too: next month, its "What we said" column becomes part of what you check against.