Product and project management · Advanced · 17 min
Forecast delivery dates from past throughput
By Padding · Updated 18 Nov 2026
Google Sheets or Microsoft Excel · November 2026
You will build a spreadsheet that replays twelve past weeks of finished work two thousand times and answers "when will these 40 items be done?" with three dates at 50, 85 and 95 percent likelihood, ready to refresh every Monday.
On this page
Larkfield Clinic's booking and reminders work has 40 items left on the board, and the practice manager wants to know when patients can start booking online. You could estimate every item and add them up, but that takes a morning, and the total would still be one number that is almost certainly wrong. There is a quicker method that is also more honest: look at how many items the team has actually finished each week, and ask what happens if the coming weeks look like a random mix of those past weeks.
That is a Monte Carlo forecast. You replay the past at random, thousands of times, and count how often the 40 items are done by each week. The answer is not one date but a spread: "half the time by this Friday, 85 times in 100 by that one". In this tutorial you build it in a spreadsheet with three tabs and five formulas, using twelve real-looking weeks of Larkfield history.
The method rests on two assumptions. The near future resembles the recent past, and the items left are roughly the same mix of sizes as the items the team finished. You do not need every item to be the same size, only for the remaining work to be like the finished work. Step 7 covers what to do when either assumption breaks. If your team has not yet tried thinking in ranges, read estimate work with ranges instead of false precision first.
Step 1 · Collect twelve weeks of throughput
Throughput is the number of items that reached your board's Done column in a week. Count items, not story points or hours, and count only items that are finished by your team's own definition of done. Items started but not finished do not count, and nor do items cancelled.
Create a new spreadsheet with three tabs, named exactly History, Sim and Forecast. The formulas later refer to these names.
On History, put headings in row 1: Week starting in A1 and Items finished in B1. Then fill rows 2 to 13 with the last twelve complete weeks, oldest first. Larkfield's are:
| Week starting | Items finished |
| --- | --- |
| 7 Sep 2026 | 5 |
| 14 Sep 2026 | 2 |
| 21 Sep 2026 | 6 |
| 28 Sep 2026 | 0 |
| 5 Oct 2026 | 6 |
| 12 Oct 2026 | 3 |
| 19 Oct 2026 | 3 |
| 26 Oct 2026 | 6 |
| 2 Nov 2026 | 5 |
| 9 Nov 2026 | 8 |
| 16 Nov 2026 | 4 |
| 23 Nov 2026 | 6 |
The zero is the week of the clinic's annual inspection, when the team worked but shipped nothing. Keep weeks like that: they really happen, and leaving them out makes the forecast too hopeful. The exception is a planned holiday when nobody works. Leave holiday weeks out of the history and add them back in Step 5, otherwise you count them twice.
If your board tool can export finished items with a completion date, a pivot or a COUNTIFS per week gets you this column in a few minutes. If it cannot, count the Done column at the end of each week and keep a running note from now on.
Check it worked
History has twelve numbers in B2:B13, all whole numbers of zero or more, oldest at the top. Put =SUM(B2:B13) in an empty cell: for the Larkfield figures it shows 54. Delete that cell before you go on.
Step 2 · Set up the forecast inputs
Put the things you will change each week in one place, so you never edit a formula to update the forecast. On the Forecast tab, type these labels in column A and values in column B:
| Cell | Label (column A) | Value (column B) |
| --- | --- | --- |
| row 1 | Items remaining | 40 |
| row 2 | Forecast starts (a Monday) | 30 Nov 2026 |
| row 3 | Weeks off in the period | 2 |
| row 4 | Trials | 2000 |
Type the date in your own locale's format and check that the cell is treated as a date: switch its format to a number briefly, and if it shows a large whole number such as 46356, it is a date. Larkfield's team is off for the two weeks from 21 December, so B3 is 2.
Items remaining means items the team has agreed are in this piece of work, still not done. Count the items in progress as remaining, since they are not finished.
Check it worked
Forecast B1 to B4 show 40, a date that falls on a Monday, 2 and 2000. Nothing else on that tab is filled in yet.
Step 3 · Build one simulated trial
One trial pretends to live through the coming weeks. For each simulated week it picks one of the twelve past weeks at random and adds that week's count to a running total. The trial is finished when the running total reaches the items remaining.
On the Sim tab, put Week 1 in B1, Week 2 in C1 and so on to Week 26 in AA1, then Weeks needed in AB1. Twenty-six weeks is half a year of simulated time, far more than Larkfield needs, and Step 4 checks it is enough for you.
In B2, the first week picks one past week at random:
=INDEX(History!$B$2:$B$13, RANDBETWEEN(1, 12))RANDBETWEEN(1, 12) returns a whole number from 1 to 12, both included, and INDEX returns that row of the history. Every past week has the same chance of being picked, and the same week can be picked again.
In C2, each later week adds a new pick to the total so far:
=B2+INDEX(History!$B$2:$B$13, RANDBETWEEN(1, 12))Copy C2 and paste it into D2:AA2. Because B2 has no dollar signs, each cell adds to the cell on its left.
In AB2, count how many weeks it took:
=COUNTIF(B2:AA2, "<"&Forecast!$B$1)+1Every cell that is still below 40 is a week in which the work was not yet done. The week after the last of them is the week it finished, hence the +1.
Check it worked
Row 2 rises from left to right, never falls, and goes up by at most 8 at each step, the biggest week in the history. Find the first cell that is 40 or more: its week number matches AB2. Change any empty cell anywhere in the sheet (in desktop Excel, press F9) and the whole row changes, and AB2 most likely changes with it.
Step 4 · Repeat the trial two thousand times
One trial is one possible future. The forecast comes from how two thousand of them spread out.
Select B2:AB2 and copy it. Click the box to the left of the formula bar that shows the current cell address, type B3:AB2001 and press Enter to select that range, then paste. You now have 2,000 rows, each an independent trial, filling rows 2 to 2001.
Two thousand trials of 26 weeks is about 54,000 random cells, which a laptop recalculates in a moment. On an older or low-end Android phone the Sheets app can stall at this size, and every edit triggers a full recalculation, so build and refresh the sheet on a laptop or desktop and use the phone only to read the result. If a laptop also struggles, use 1,000 trials and change 2001 to 1001 everywhere below.
Make sure the horizon was long enough. On Forecast, in A5, type Trials that ran out of weeks and in B5:
=COUNTIF(Sim!$AB$2:$AB$2001, 27)A value of 27 in column AB means the trial was still short of 40 after 26 weeks. If B5 is anything other than 0, the weeks columns are too few: extend the Sim formulas further right, and change AA and 27 in every formula to match.
Check it worked
Sim has formulas in every cell from B2 to AB2001, and column AB holds whole numbers, mostly between 7 and 13 for the Larkfield figures. Forecast B5 shows 0.
Step 5 · Turn trials into dates
Now read the spread. If 85 percent of trials finished within some number of weeks, that number is the 85 percent forecast.
On Forecast, put headings in row 7: Likelihood in A7, Working weeks in B7, Done by (Friday) in C7. In A8, A9 and A10, type 0.5, 0.85 and 0.95, and format them as percentages.
In B8:
=ROUNDUP(PERCENTILE.INC(Sim!$AB$2:$AB$2001, A8), 0)PERCENTILE.INC can return a fraction when the cut falls between two values, and you cannot finish part of the way through a week, so round it up.
In C8, turn weeks into a calendar date, adding the weeks off and landing on the Friday of the finishing week:
=$B$2+7*(B8+$B$3)-3Format C8 as a date, then copy B8:C8 down into B9:C10.
For Larkfield, starting Monday 30 November 2026 with two weeks off, the results are:
| Likelihood | Working weeks | Done by |
| --- | --- | --- |
| 50% | 9 | Fri 12 Feb 2027 |
| 85% | 11 | Fri 26 Feb 2027 |
| 95% | 12 | Fri 5 Mar 2027 |
Notice the 50 percent row. Larkfield averages 4.5 items a week, and 40 divided by 4.5 is a little under 9 weeks. A forecast built on the average gives you the date the team hits half the time: a coin toss presented as a plan.
Under the dates, add a table that shows the whole curve. In A12 type Within weeks and in B12 Chance. Fill A13:A23 with the numbers 6 to 16, and in B13:
=COUNTIF(Sim!$AB$2:$AB$2001, "<="&A13)/COUNT(Sim!$AB$2:$AB$2001)Format B13 as a percentage and copy it down to B23.
Check it worked
For the Larkfield figures, B8:B10 read 9, 11 and 12, and C8:C10 show Fridays in February and March 2027. The Chance column rises from close to 0 percent to 100 percent, never falls, and reads something like 58 percent at 9 weeks, 92 percent at 11 and 97 percent at 12.
Step 6 · Re-run the simulation and test its stability
A forecast that jumps around every time you recalculate is not ready to share. Recalculate five times: change any empty cell and delete it again in Google Sheets, or press F9 in desktop Excel. Watch C9, the 85 percent date, each time.
With 2,000 trials the percentages in the Chance column move by a point or so each run. A date only moves when one of those percentages sits right at a boundary, for example 84.6 percent at 11 weeks. When that happens the date flips by a whole week between runs, because the trials count in whole weeks. You have three ways to deal with it:
- Raise the trials to 5,000 by filling more rows and updating every
2001, which narrows the wobble. - Report the later of the two dates. It is the cautious choice, and you are not claiming more certainty than the data gives you.
- Look at the
Chancecolumn and quote the real figure next to the date, for example "84 to 86 percent by that Friday".
Check it worked
Across five recalculations the 85 percent date in C9 stays the same, or moves by exactly one week and back. For the Larkfield figures it stays on 26 February 2027 every time. If it moves by two weeks or more, something is wrong: check that every formula points at rows 2 to 2001 and at History!$B$2:$B$13.
Step 7 · Know when the forecast will mislead you
The spreadsheet works out the arithmetic for you, but it cannot tell when the inputs have stopped describing your team. Before you share a date, check for these:
- The team changed. Someone joined, left or moved to other work. The old weeks describe a different team. Drop the weeks before the change if you have at least six left, and say plainly that the forecast rests on a short history.
- The remaining items are bigger than the finished ones. If the last 40 include "integrate with the national patient record system" while the history was mostly small fixes, the forecast will be early. Split large items until they look like the items the team usually finishes; split a large user story into thin slices shows how. Then update the count.
- Scope keeps growing. The forecast covers the 40 items you know about. If Larkfield's list grew by three items a week over the last month, the real remaining work is a moving target. Track the count every Monday, and when it keeps rising, say so next to the date.
- The definition of done drifted. If "done" once meant "merged" and now means "live for patients", old and new weeks are not comparable.
- Too little history. With fewer than six weeks you have very few futures to draw from. Use the forecast as a rough guide and keep collecting.
- Too much work in progress. A team that starts everything at once finishes in bursts, which widens the spread. Limiting work in progress, covered in run a Kanban board with WIP limits, makes weekly throughput steadier and the forecast tighter.
Check it worked
Write one line under the dates on Forecast, starting "Assumes:", that names what the forecast depends on. For Larkfield: "Assumes: same five people, items split to under three days, scope fixed at 40, two weeks off at Christmas." Each item in the list above is either answered by that line or noted as a known risk next to it.
Step 8 · Present the forecast and refresh it weekly
Give a date with its likelihood, and never the 50 percent date alone. Lead with the 85 percent date, since that is the one people plan around. The 95 percent date is for commitments that are costly to miss, such as a date printed on patient letters. For Larkfield's weekly update:
Online booking: 85 percent likely by Friday 26 February 2027, and very likely (95 percent) by 5 March. There is an even chance of 12 February. Based on the last 12 weeks of finished work and 40 items left. Next update Monday 7 December.
The words "85 percent likely" do the work that "should be done by" used to do, while telling people how much to lean on the date. If a stakeholder wants one date, give the 85 percent date and keep the likelihood attached when they repeat it. Write a weekly stakeholder update covers where this line goes.
Every Monday, refresh the sheet in about five minutes:
- On
History, copy B3:B13, then paste them into B2 as values only, so each week moves up a row and the oldest drops off. Type last week's count into B13 and update the week dates in column A. - On
Forecast, set B1 to the items now remaining, B2 to today's Monday, and B3 to the weeks off that are still ahead. - Recalculate a couple of times and confirm the dates are stable, as in Step 6.
- Add a tab called
Log, and paste the date, items remaining and the three forecast dates as values only, one row per week.
Pasting into the same cells keeps every formula pointing at History!$B$2:$B$13. Deleting and inserting rows inside that range can shrink or move it.
Check it worked
Your Log tab has a row for this week with today's date, the items remaining and three dates. After a few weeks the log shows whether the 85 percent date is holding or drifting later, which is the trend to report when the plan is in trouble.
Next steps
You now have a forecast sheet that turns twelve weeks of history into three dated likelihoods and can be refreshed in minutes. To go further:
- Estimate work with ranges instead of false precision helps when there is no history yet, such as a brand-new team.
- Run a Kanban board with WIP limits makes throughput steadier, so the spread between the 50 and 95 percent dates narrows.
- Keep a roadmap honest when plans change shows how to update a roadmap when the 85 percent date moves.
- Write a weekly stakeholder update turns the forecast and its log into a short note people read.
Related tutorials
- Write user stories with clear acceptance criteriaYou will have five user stories for a clinic's reschedule feature, each checked against INVEST and carrying Given / When / Then acceptance criteria that a developer and a tester read the same way.
- Write tickets developers want to pick upYou will rewrite three vague backlog tickets into ones a developer can start without asking a question, and save the structure as a ticket template in your tracker.
- Write a weekly stakeholder update people readYou will have a reusable weekly update template and one finished update under 250 words, whose first two lines tell any reader whether they need to act.