Estimate work with ranges instead of false precision

By Padding · Updated 18 Nov 2026
Any spreadsheet · November 2026

You will estimate the Larkfield Clinic booking slices three ways, compare what each tells a stakeholder who asks "when", and finish with a ranged estimate that has a low bound, a high bound and the written assumptions behind it.

On this page

The clinic manager at Larkfield asks a fair question: "When can patients book online?" A developer, wanting to help, says "about six weeks". Nobody writes that down, yet a month later it has become "you promised six weeks", and the conversation is about blame instead of what the team has learned.

A single number sounds like a commitment, whatever the person saying it meant. It hides how sure you are and gives the listener no way to plan for the bad case. A range with stated assumptions says the same thing honestly: this is what we know, this is what we do not, and this is what would change the answer.

This tutorial uses the Larkfield Clinic online booking work, already split into nine thin slices and a spike in Split a large user story into thin vertical slices. You estimate the slices three ways (t-shirt sizes, story points with planning poker, and best, likely and worst ranges), see what each one tells the clinic manager, then write a ranged answer to "when" with its assumptions. You also plan when to re-estimate, because a range should get narrower as the team learns.

Step 1 · Set up the estimation sheet

Open a new spreadsheet called "Larkfield booking: estimates". In row 1 put these headings, one per column from A to H:

Text
Slice | T-shirt | Points | Best (days) | Likely (days) | Worst (days) | Biggest unknown | Above cut line?

Put one slice per row from row 2. For Larkfield, in delivery order:

Text
0  Spike: can we read and write the clinic diary?
1  Patient sees this week's open GP times
2  Registered patient books an open GP time
3  Patient cancels with their booking reference
4  Nurse appointments
5  New patient requests a first visit
6  Booking pages in the clinic's second language
7  Parent books for a child on their record
8  Open times sync from the clinic diary
9  Handle Monday 8am demand

Mark slices 0 to 6 "yes" in column H and slices 7 to 9 "no". That is the cut line from the splitting tutorial: the release the clinic would accept, and the extras.

Agree one unit before anyone estimates. In this tutorial, a "day" means one working day of the whole small team (two developers and a tester) on that slice, not a calendar day. Write that definition in a note under the table. Most estimating arguments are really two people using different units.

Check it worked

Your sheet has ten slice rows, eight headings and a written definition of "day". Read the definition to one person who will build the work; if they say "do you mean my days or the team's?", the note is not clear yet. Rewrite it until they can repeat it back.

Step 2 · Size every slice with t-shirt sizes

T-shirt sizing is the fastest way to see the shape of the work. Use four sizes and agree what they mean against one slice everyone understands:

  • S: about the same as slice 3 (cancel with a reference). Small, well understood.
  • M: two or three times an S.
  • L: a week or more of team effort, with some unknowns.
  • XL: too big or too unclear to size. An XL is a signal to split or investigate, not a size.

Go down the list with the team and call out a size for each slice. Do not discuss for more than a minute; if two sizes are close, take the larger. For Larkfield the team says:

Text
0 S (time-boxed)   1 S   2 M   3 S   4 S   5 M   6 M   7 S   8 XL   9 M

Fill column B. Now picture saying this to the clinic manager: "It's mostly small and medium, with one extra-large." That is useful for one thing: it points straight at slice 8 as the risk. It says nothing about a date, and a manager who hears "mostly small" may assume "soon".

Check it worked

Every row has a size in column B, and at least one slice is marked as the reference S. If any slice other than the spike is XL, write why in column G (for slice 8: "nobody knows whether the diary system allows other software to connect").

Step 3 · Estimate in story points with planning poker

Story points measure how big a slice is relative to the others, combining effort, complexity and risk. They are not hours. Planning poker is a way to get them from the whole team without the first voice setting everyone's answer.

Each estimator has cards with 1, 2, 3, 5, 8 and 13, plus a "?" card for "I do not understand this slice well enough". The gaps widen on purpose: the bigger the work, the less precisely anyone can size it. For each slice:

  1. The product manager reads the slice and its acceptance criteria. People ask questions.
  2. Everyone chooses a card privately.
  3. Everyone reveals at the same time.
  4. If the cards differ, the highest and lowest estimators explain their thinking first. The high card often knows about hidden work; the low card may know a shortcut.
  5. Vote again. Stop after two or three rounds; if cards are still far apart, the slice needs splitting or a question answered.

Do not average the cards. If one developer shows 3 and another 13 on slice 6, the average of 8 hides the actual finding: one of them knows the translated text is longer than English and breaks the booking form on a small phone screen, and the other did not. Write that finding in column G.

If your team works from different places, as many teams across Africa do, run the vote over chat: each person sends their card privately to the facilitator, who posts all of them at once. That keeps the reveal simultaneous and works on a phone with little data, without a video call.

For Larkfield the agreed points are:

Text
0 2 (time-boxed)   1 2   2 5   3 1   4 2   5 5   6 5   7 2   8 ?   9 3

Fill column C. Slices 0 to 6 add up to 22 points. Now picture telling the clinic manager "the first release is 22 points". The number is precise and means nothing to anyone outside the team. Converting it to a date needs to know how many points the team finishes a week, which a new team does not yet know.

Check it worked

Every row has points or a "?" in column C. Column G has at least one finding that came out of a high-low discussion, written as a fact ("translated labels are up to 40% longer; form must wrap on 360px screens"), not as "disagreed". If every slice got the same card from everyone on the first vote, ask whether people were choosing privately.

Step 4 · Give each slice a best, likely and worst range

Now estimate in the unit the clinic manager cares about: days, as you defined them in the first step. For each slice, ask three questions in this order:

  1. Best: if everything goes as hoped, how many days?
  2. Worst: if the problems we can already imagine all happen, how many days? (Not "if the building burns down": real, nameable problems.)
  3. Likely: what do you expect?

Ask for worst before likely. People anchor on their first answer, and a "likely" given first tends to drag the worst case down towards it.

For Larkfield:

Text
Slice  Best  Likely  Worst  Why the worst is high
0      2     2       2      Time-boxed: stops at two days whatever it finds
1      2     3       5      First slice; hosting and deploy set-up happen here
2      4     6       10     Matching patients to the register is unclear
3      1     2       3
4      2     3       5
5      3     5       9      Approval rules depend on reception staff we have not met yet
6      3     5       10     Translation turnaround; long text on small screens
7      2     3       6
8      5     10      25     Depends entirely on the spike
9      2     4       10     No real demand data until slices 1 to 3 are live

Fill columns D, E and F. Notice what the ranges show that the other methods did not. Slice 3 has a narrow range: the team knows what to do. Slice 8 spans five times from best to worst: it is a guess until the spike reports. Points gave slices 2 and 6 the same 5, but the ranges say slice 6 is the less certain of the two.

Check it worked

Every row has three numbers with best less than or equal to likely, and likely less than or equal to worst. Every slice whose worst is more than twice its best has a reason in the last column. If any slice has best, likely and worst all equal (other than the time-boxed spike), ask the team what could go wrong; a range with no width is a single number in disguise.

Step 5 · Add up the release and turn it into weeks

Below the table, add totals for the slices above the cut line. If slices 0 to 6 are in rows 2 to 8, use:

Text
Best total:   =SUM(D2:D8)
Likely total: =SUM(E2:E8)
Worst total:  =SUM(F2:F8)

For Larkfield that gives 17, 26 and 44 team-days.

Adding every slice's best case gives a total that is almost certainly too optimistic, and adding every worst case gives one that is almost certainly too pessimistic: not every slice goes well, and not every slice goes badly. Treat 17 to 44 as the outer edges. The answer you give will sit inside them.

Now convert days to weeks. The team does not spend five days a week on slices: there is support, meetings, and the clinic's other systems. Ask the team how many team-days of slice work they get in a normal week, and write the answer as an assumption. Larkfield's team says about four. That gives:

Text
Best:   17 / 4 = about 4.5 weeks, round up to 5
Likely: 26 / 4 = about 6.5 weeks, round up to 7
Worst:  44 / 4 = 11 weeks

Round up and use whole weeks. "6.5 weeks" sounds more precise than anything here deserves.

Check it worked

Your sheet has three totals for the slices above the cut line, a stated number of slice-days per week, and the totals in whole weeks. The best and worst totals are clearly different; for a release with a known unknown, expect the worst to be at least twice the best. If yours are close, look again at the slices with the most open questions.

Step 6 · Compare what each method tells the person asking "when"

Write three short sentences, one per method, as you would say them to the clinic manager:

  • T-shirt: "It's mostly small and medium pieces, with one large unknown, the diary connection, which we have left out of the first release."
  • Points: "The first release is 22 points."
  • Range: "The first release is 5 to 11 weeks from when we start, most likely about 7. We'll narrow that after the two-day spike and again once patients can book a GP time."

Read them side by side. T-shirt sizes are good for spotting risk and deciding what to split, and they cost almost nothing. Points help the team compare work against itself, but they are internal currency; turning them into dates needs a track record the team does not have yet. The range answers the question asked, shows the uncertainty, and tells the listener when it will improve.

Use the first two inside the team. Use the range when anyone outside the team asks "when".

Notice too what "6 weeks" would have done. It falls between the best and likely cases, so the team has a better-than-even chance of missing it, and it says nothing about the worst case the clinic might need to plan for, such as keeping extra phone cover at reception.

Check it worked

You have three sentences written below the sheet. Give the range sentence to someone outside the team and ask: "What is the earliest and latest this could be ready, and when will we know more?" If they answer 5 weeks, 11 weeks and "after the spike", the sentence works. If they say "seven weeks", move the low and high numbers to the start of the sentence.

Step 7 · Write the assumptions behind the range

A range is only honest if the listener can see what it rests on. Under the sentence, add a heading "This estimate assumes" and list every assumption that, if wrong, would move the numbers. For Larkfield:

  1. The team stays at two developers and a tester, with about four team-days a week on booking work.
  2. Slices 7, 8 and 9 are not in the first release.
  3. The clinic's receptionists can spend an hour a week answering questions and testing slices.
  4. Translated text for slice 6 arrives within five working days of being requested.
  5. Hosting can be set up on the clinic's existing account without a new procurement process.
  6. Matching a booking to a registered patient by name, date of birth and phone number is acceptable to the clinic; no ID check is needed.

Each assumption should be something the clinic manager can confirm, deny or act on. "Nothing goes wrong" is not an assumption. "Translations arrive within five days" is, and the manager can make it true.

Send the range, the assumptions and the date of the estimate together, in writing, as one message. That stops the range being quoted later without the conditions attached.

Check it worked

Your estimate has a low bound, a high bound and at least three written assumptions, each one specific enough that someone could tell you it is wrong. Point to the one assumption that would move the high bound most if it failed; for Larkfield it is the translation turnaround. If you cannot pick one, your assumptions are too general.

Step 8 · Re-estimate as the unknowns are removed

The cone of uncertainty describes what you just saw. At the very start of a project, an estimate can be several times too high or too low. The range narrows as decisions are made and unknowns are answered, but only then: time passing does not narrow it on its own, and a badly run project can stay just as uncertain for months.

So plan the points where you will re-estimate, and say them out loud. "We'll know more after the spike" is a real answer when it comes with a date. For Larkfield, re-estimate at two moments:

After the spike (end of week 1). The spike finds that the diary system can export open times but not accept bookings. Slice 8 changes from "sync both ways" to "read open times only"; its range goes from 5 to 25 days down to 4 to 8. Slice 8 is still below the cut line, so the first-release range does not move, but the clinic now knows the full picture is smaller than feared.

After slices 1 and 2 ship (around week 3 or 4). You now have real numbers. Suppose slices 0 to 2 took 12 days against a likely total of 11. Re-estimate the remaining slices 3 to 6 with what you learned. The translator has confirmed a three-day turnaround, so slice 6 drops from 3 to 10 days to 3 to 6. The remaining work becomes 9 to 23 days, or 3 to 6 weeks from now. Add that to the weeks already spent and the release range has narrowed to about 6 to 9 weeks from the start.

Add a column for each re-estimate rather than overwriting the old numbers, and write the date at the top. Seeing the old range next to the new one shows the clinic manager the cone narrowing, and shows why it narrowed.

Once a few slices are done, you have something better than estimates: the team's real pace. Forecast delivery dates from past throughput shows how to use it.

Check it worked

Your sheet has at least one planned re-estimate with a date and a trigger ("after the spike", "after slice 2 ships"). If you have done one, the new columns sit next to the old ones, and the new release range is narrower than the first and still lies within the original outer edges. If it got wider, write down which assumption failed and send that to the clinic manager the same day.

Next steps

Once a handful of slices are finished, replace guesswork with the team's real pace using Forecast delivery dates from past throughput. If a slice's range is too wide to be useful, go back and cut it thinner with Split a large user story into thin vertical slices. When the high bound is later than the clinic can accept, agree what to leave out with Agree what goes in a release with MoSCoW. To make each slice clear enough that estimates stop swinging between 3 and 13, write it up with Write tickets developers want to pick up.