Run two-week sprints with Scrum

By Padding · Updated 18 Nov 2026
Any calendar and board tool · November 2026

You will set up Scrum for a five-person team from the 2020 Scrum Guide and end with a two-week sprint calendar showing every event and its timebox, a board holding the three artifacts, and a written definition of done.

On this page

Many teams say they "do Scrum" when what they do is a fortnightly ticket list, a long daily status meeting and a burn-down chart nobody reads. Then Scrum gets the blame when it does not help. The Scrum Guide itself is short and sets out a small number of fixed parts: three accountabilities, five events and three artifacts, each with a commitment attached. Everything else, including story points and velocity charts, is something teams add.

In this tutorial you set up Scrum for one team, part by part, from the 2020 Scrum Guide. The running example is Larkfield Clinic, the fictional community clinic that is building online booking and SMS appointment reminders. Its delivery team has five people: Ngozi, the clinic's operations lead, plus Tomás, Achieng, Dev and Lindiwe. You will decide who holds which accountability, write the product goal and a definition of done, put a two-week sprint on the calendar with every timebox, set up the board, and write down which extras the team chose on top of the Guide.

Use your own team if you have one. Keep the Guide open as you go: wherever this tutorial says "the Guide requires", you can find the sentence there.

Step 1 · Name who holds each accountability

The Guide defines three accountabilities, not job titles:

  • Product Owner: accountable for getting the most value out of the team's work, and for the product backlog. The Guide is explicit that this is one person, not a committee.
  • Scrum Master: accountable for the team using Scrum well, helping the team and the wider organisation understand it and removing things that block progress.
  • Developers: everyone who does the work of creating each increment. The Guide defines them by the work, not by title, so designers, testers and analysts who help create the increment count as Developers, not only people who write code.

Together they form one Scrum Team, typically ten people or fewer, with no sub-teams or hierarchy inside it.

Write a short table at the top of a team document called "How we run Scrum". For Larkfield:

| Accountability | Person | Notes |
| --- | --- | --- |
| Product Owner | Ngozi | Decides backlog order; has time blocked for the team every day |
| Scrum Master | Tomás | Also a developer for about half his time |
| Developers | Tomás, Achieng, Dev, Lindiwe | Two engineers, a designer and a tester |

The Guide does not forbid one person holding two accountabilities, and small teams often combine Scrum Master and Developer. What it does not allow is a product owner by committee. If the clinic manager, the head doctor and Ngozi all expect to set priorities, settle now that Ngozi decides and the others feed into her.

Check it worked

Your document names exactly one Product Owner. Every person on the team appears in the table, and anyone who will build, design or test is listed as a Developer. If someone you depend on is missing from the table (an outside supplier, for example), add a note saying how they will join in.

Step 2 · Write the product goal

Each artifact in the Guide has a commitment, something it is measured against:

  • the product backlog commits to the product goal
  • the sprint backlog commits to the sprint goal
  • the increment commits to the definition of done

Start with the product goal, because it is what the backlog is ordered towards. It is the team's long-term objective: one target, reached over many sprints, which the team finishes (or abandons) before taking on the next.

Write it as one or two sentences that say who benefits and how you will know it is reached. Larkfield's:

Patients can book, move and cancel their own appointments online, and get an SMS reminder the day before, so that fewer than 1 in 20 appointments are missed without notice.

Put it under the accountability table, and copy it to the top of your board so it is visible every time someone opens it.

Check it worked

Read the goal to someone outside the team. They can tell you who it helps and what would show it is done, without asking what any term means. If your goal is a list of features ("booking page, reminders, admin panel"), rewrite it as the change those features are meant to cause.

Step 3 · Write the definition of done

The definition of done is the quality bar every piece of work must reach before it counts as part of the increment. The Guide says work that does not meet it cannot be shown at the sprint review and goes back to the product backlog. That makes it the commitment that stops "nearly done" from piling up.

Write it with the Developers, not for them, because they are the ones required to meet it. Keep it to checks a person can confirm with a yes or no. Larkfield's first version:

  1. The change has been reviewed by a developer who did not write it.
  2. Automated tests for the change pass, and so do the existing ones.
  3. It works on the cheapest Android phone the clinic keeps for testing, on a throttled 3G connection, because many patients book on low-end phones with prepaid data.
  4. Every screen can be used with a screen reader and keyboard alone.
  5. Patient-facing text, including SMS wording, has been checked in every language the clinic offers.
  6. It is deployed to the staging site and Ngozi can try it there.
  7. No patient data appears in logs or error reports.

Add it to the "How we run Scrum" document, with a date and a line saying the team reviews it at each retrospective. A definition of done usually grows as the team gets better at meeting it.

Check it worked

Pick any item the team finished recently and go down your list. You can answer yes or no to every line without arguing about what it means. If a line needs a judgement call ("code is clean", "well tested"), replace it with something observable.

Step 4 · Fix the sprint length and put the events on the calendar

The sprint is itself an event: a fixed-length period of one month or less that holds the other four events. A new sprint starts as soon as the last one ends. Larkfield chooses two weeks, which gives the clinic a chance to change direction every ten working days without making the events feel constant.

The Guide sets maximum timeboxes for a one-month sprint and says that for shorter sprints the events are usually shorter. It does not give two-week figures. Many teams halve them, which gives these caps:

| Event | Guide maximum, one-month sprint | Larkfield cap, two-week sprint | Who attends |
| --- | --- | --- | --- |
| Sprint | One month or less | 10 working days | Whole Scrum Team |
| Sprint Planning | 8 hours | 4 hours | Whole Scrum Team |
| Daily Scrum | 15 minutes | 15 minutes | Developers (PO and SM join as Developers if they are working on sprint items) |
| Sprint Review | 4 hours | 2 hours | Scrum Team and invited stakeholders |
| Sprint Retrospective | 3 hours | 1.5 hours | Whole Scrum Team |

A cap is a limit, not a target. Larkfield books slightly less than each cap and ends early when an event's purpose is met.

Now create the calendar. Larkfield starts sprints on a Wednesday, so that the end of a sprint does not fall on a Monday or a Friday, the days most likely to be lost to leave or public holidays. Holidays differ between countries, so if your team spans several (Nigeria and Kenya, say), check both calendars for the coming quarter and move a sprint boundary rather than lose a review.

| Day | Date pattern | Event | Time |
| --- | --- | --- | --- |
| 1 | Wednesday, week 1 | Sprint Planning (max 4 h) | 09:30–12:30 |
| 1 | Wednesday, week 1 | Daily Scrum (15 min) | 14:00–14:15 |
| 2–9 | Thursday to the next Monday | Daily Scrum (15 min) | 09:30–09:45 |
| 6 | Wednesday, week 2 | Backlog refinement (activity, not an event) | 14:00–15:00 |
| 10 | Tuesday, week 2 | Daily Scrum (15 min) | 09:30–09:45 |
| 10 | Tuesday, week 2 | Sprint Review (max 2 h) | 13:00–14:30 |
| 10 | Tuesday, week 2 | Sprint Retrospective (max 1.5 h) | 15:00–16:00 |

Create each one as a recurring event in your calendar tool, repeating every two weeks (the Daily Scrum repeats every working day). Put the timebox in the event title, as shown, and put one line of purpose in the description: "Planning: agree why this sprint matters, what we will do and how." The Guide asks for the Daily Scrum at the same time and place every day, so give it one fixed video link or room.

Copy the event table and the calendar table into the "How we run Scrum" document under a heading "Sprint calendar", so the plan is written down as well as booked.

Two details matter. The review comes before the retrospective, because the Guide makes the retrospective the event that closes the sprint. And refinement is shown as an activity, because the Guide describes it as ongoing work rather than one of the five events; a fixed slot stops it being forgotten.

If someone on the team often joins on mobile data, agree that they can join the Daily Scrum by audio only, and keep a written board walk-through for days when the connection fails. The stand-up tutorial linked at the end covers a written format.

Check it worked

Open your calendar on a two-week view. You can see all five events (the sprint itself as an all-day or banner entry from day 1 to day 10, plus planning, ten Daily Scrums, the review and the retrospective), each with its timebox in the title. No event is booked longer than its cap. The next sprint's planning sits on the working day straight after this sprint's retrospective, with no gap.

Step 5 · Set up the board to hold the three artifacts

Your board needs to make the three artifacts easy to tell apart.

  • Product backlog: the single ordered list of everything that might be done to the product. Ngozi orders it. Only the top few items need to be small and clear enough to pull into a sprint.
  • Sprint backlog: the sprint goal, the items the Developers chose in planning, and their plan for delivering them. It belongs to the Developers, and they update it throughout the sprint.
  • Increment: the work that meets the definition of done. More than one increment can be made in a sprint, and an increment can be released before the review.

On most board tools this works as one board with columns, plus a separate list or view for the product backlog. For Larkfield:

  • A Product backlog list, with the product goal pinned at the top.
  • A Sprint board with columns To do, In progress, In review, Done. The sprint goal is written in the board's description or a pinned card, not just in a meeting note.
  • Done means "meets the definition of done". Link the definition from the column's description so nobody has to guess.

When you have written your sprint goal in planning, put it where the Developers will see it every day. The goal is the commitment, not the list of tickets: the Guide lets the Developers change the plan during the sprint as long as the goal holds.

In the "How we run Scrum" document, add a short section called "Board": a link to the board, its columns, and where the product goal, sprint goal and definition of done live on it.

Check it worked

Someone new to the team can open the board and answer three questions without asking: what is the product goal, what is this sprint's goal, and what does "Done" mean here. Each answer is written on the board or one click away from it.

Step 6 · Write down what you add on top of Scrum

The Guide deliberately leaves a lot out. Teams fill the gaps with practices, and that is fine, as long as everyone knows which parts are Scrum and which are the team's own choices. Otherwise a team that drops story points thinks it has stopped doing Scrum, or a manager treats velocity as something the Guide demands.

Add a section to your team document headed "Our additions (not required by the Scrum Guide)". For Larkfield:

  • User stories with acceptance criteria to describe backlog items. The Guide does not say how items are written.
  • Story points for rough sizing in refinement. The Guide does not mention story points.
  • Velocity (points finished per sprint), used by the Developers only to sanity-check how much to pull in. The Guide does not mention velocity. It is never compared between teams or used as a performance target.
  • A burn-down chart on the sprint board. The Guide names burn-downs, burn-ups and cumulative flow as forecasting practices, and adds that they do not replace looking at what actually happened.
  • The three-question stand-up (yesterday, today, blockers). Not in the 2020 Guide, which leaves the Daily Scrum's format to the Developers. Larkfield replaced it with walking the board.
  • A fixed refinement slot on day 6, as on the calendar.

Next to each addition, write one line saying why the team uses it. Anything nobody can justify is a candidate to drop at the next retrospective.

Also write the few rules from the Guide that teams often forget, so they are easy to find:

  • Only the Product Owner can cancel a sprint, and only if the sprint goal has become obsolete.
  • Work that does not meet the definition of done is not shown at the review.
  • During the sprint, no changes are made that would endanger the sprint goal; the plan for reaching it can change.

Check it worked

Your team document now has two clearly separated parts: the Scrum parts (accountabilities, product goal, definition of done, events and artifacts) and a list of additions, each with a reason. Show it to one teammate and ask them to point to a line they would drop. If they can name one and explain why, the list is doing its job.

Step 7 · Review the setup before the first sprint starts

Before day 1, spend thirty minutes going through the setup with the whole team. You are not running an event yet; you are checking that everyone reads the same document the same way.

Walk through it in this order and fix gaps on the spot:

  1. The accountability table: does everyone agree with their role, and does Ngozi have time blocked for the team?
  2. The product goal: can each person say it back in their own words?
  3. The definition of done: can the Developers meet every line with the tools they have? A line about testing on a low-end Android phone needs that phone on someone's desk.
  4. The calendar: has everyone accepted every recurring event, and are the stakeholders invited to the review?
  5. The board: is the top of the product backlog ready for planning, with items small enough to finish inside a sprint?

Write the date of this review and "first sprint starts" with its date at the top of the document.

Check it worked

Every team member has accepted the recurring events, so your calendar shows no pending invitations. Your "How we run Scrum" document has all six parts in it (accountabilities, product goal, definition of done, sprint calendar, board layout, additions), and the first sprint's planning is on the calendar with the top of the backlog ready.

Next steps

You now have the frame of Scrum in place: who decides what, the goal the backlog serves, a quality bar, and a calendar that keeps every event in its timebox. Each event then needs to be run well.