Product and project management · Beginner · 13 min
Run a sprint planning meeting that ends with a goal
By Padding · Updated 18 Nov 2026
Any board tool · November 2026
You will prepare and run a two-week sprint planning meeting and leave with a one-sentence sprint goal, a sprint backlog the developers chose and a capacity sheet that shows the sums.
On this page
Most sprint planning meetings fail before they start. The backlog is half written, nobody knows who is on leave, and the team spends three hours estimating tickets it has never seen. It ends with a list of tickets and no reason for choosing them, so when something goes wrong in week two, nobody knows what can be dropped.
A good planning meeting is short because most of the work happens beforehand, and it ends with one thing the team commits to: a sprint goal. The 2020 Scrum Guide calls the sprint goal the "single objective for the Sprint" and makes it the commitment for the sprint backlog. The tickets are the team's current plan for reaching it, and the plan is allowed to change. The goal is not.
The running example is Larkfield Clinic, the fictional community clinic building online booking. Its Scrum team has five people: Ngozi, the product owner; Tomás, the Scrum Master, who is also a developer for about half his time; and Achieng, Dev and Lindiwe, the other developers. Between them the four developers are two engineers, a designer and a tester. Sprint 1 delivered the list of free appointment slots. You are preparing Sprint 2, which runs for two weeks. If you have not set up sprints yet, start with running two-week sprints with Scrum and come back.
You will produce three things: a capacity sheet, a sprint goal and a sprint backlog. Keep all three in one place, such as a page in your board tool or a shared document linked from the sprint.
Step 1 · Refine the top of the backlog the week before
Planning goes badly when the team meets an item for the first time in the meeting. About a week before planning, the product owner and at least one developer look at the top of the backlog together, for about an hour. Larkfield uses its fixed refinement slot on day 6 of the current sprint, Wednesday of week 2 from 14:00 to 15:00, which leaves a week to split or clarify anything that is not ready before the next sprint's planning on day 1.
Take enough items to fill roughly one and a half sprints, so the team has a real choice. For each one, check four things:
- It describes an outcome someone can see, not a technical task. "Patient books a slot with name, date of birth and mobile number", not "Build POST /bookings".
- It has acceptance criteria a tester could check. See user stories with acceptance criteria if yours do not.
- It has a rough estimate from the developers, in whatever unit the team uses. Larkfield uses developer-days.
- It can be finished inside one sprint. The Scrum Guide says items that can be done within one sprint are "deemed ready for selection". Anything bigger gets split now, not in the meeting.
Larkfield's top of backlog after refinement, in the order Ngozi set:
- Patient books a slot with name, date of birth and mobile number: 4 days
- Booking appears in the clinic's appointment system, with no double booking: 6 days
- Confirmation screen with a booking reference: 1 day
- Privacy notice and consent wording on the booking form: 1 day
- Form works on a low-end Android phone and with a keyboard or screen reader: 3 days
- SMS confirmation after booking: 2 days
- Patient cancels from a link in the confirmation: 3 days
- Patient enters a preferred doctor in a notes field: 1 day
That is 21 days of work, against a team that will turn out to have room for about 16.
Check it worked
Every item in the top group has acceptance criteria and an estimate, and none is bigger than a sprint. The total is noticeably more than one sprint's worth, so the team will have to choose.
Step 2 · Build the capacity sheet
Capacity is how much time the developers actually have this sprint, after everything that is not sprint work. Work it out the day before, with the developers, in a small table. Use one row per developer and these columns:
- Working days in the sprint. Ten for a two-week sprint with no public holidays.
- Leave and holidays. Booked leave, public holidays, training days.
- Duty. Support rota, on-call, interviewing. Count the real share of the day it takes.
- Meetings. Scrum events and regular meetings. About one day per person per two weeks is typical.
- Available days. The first column minus the other three.
Larkfield's Sprint 2 capacity sheet:
| Developer | Working days | Leave | Duty | Meetings | Available |
| --- | --- | --- | --- | --- | --- |
| Tomás | 10 | 0 | 5 (Scrum Master, about half his time) | 1 | 4 |
| Achieng | 10 | 2 | 0 | 1 | 7 |
| Dev | 10 | 0 | 3.5 (support rota, half days for 7 days) | 1 | 5.5 |
| Lindiwe | 10 | 3 (two days' leave and a public holiday) | 0 | 1 | 6 |
| Total | 40 | 5 | 8.5 | 4 | 22.5 |
Available days are not the same as days of estimated work the team can finish. Estimates are always a little optimistic, and interruptions happen. Look at the last sprint: Larkfield had 24 available days in Sprint 1 and finished items estimated at 17 days, a ratio of about 0.7. Apply it to this sprint and write the result at the bottom of the sheet:
Forecast: 22.5 available days × 0.7 ≈ 16 days of estimated work.
The Scrum Guide says developers forecast more confidently the more they know about "their past performance, their upcoming capacity, and their Definition of Done". The ratio is a common way of using past performance; it is a team habit, not something Scrum requires. If this is your first sprint, use 0.6 and adjust after the retrospective.
Where your team works across countries, add each person's public holidays, not only the office's. Larkfield's developers are split between two cities, so the sheet lists holidays by location.
Check it worked
The capacity sheet has one row per developer, a total of available days, and a forecast written as a sum anyone can follow. Each developer has confirmed their own row.
Step 3 · Draft a proposed sprint goal
The Scrum Guide gives the first move in planning to the product owner, who "proposes how the product could increase its value and utility in the current Sprint". Do that work the day before, so the meeting starts with a draft rather than a blank page.
Look at the top of the backlog and the forecast together. Ask: what is the most valuable thing someone outside the team could see at the end of these two weeks, that fits in about 16 days? Write it as one sentence that describes a result, not a list of work.
Ngozi's draft for Sprint 2:
By the end of the sprint, a patient can book a free slot on their phone and the booking appears in the clinic's appointment system, with no chance of the same slot being booked twice.
Compare it with goals that do not work:
- "Complete LB-14 to LB-21." This is a list of tickets. Nobody outside the team can tell what it means.
- "Make progress on booking." There is no point at which it is met.
- "Deliver booking, cancellation, SMS and accessibility." Four goals in one sentence. When time runs short, the team cannot tell which to protect.
Test your draft with one question: could someone who has never seen your board read it and say on the last day whether it was met? If not, rewrite it.
A proposed goal is a proposal. The whole team shapes the final wording in the meeting.
Check it worked
You have one sentence, with no ticket numbers, describing something a person outside the team could watch happen. The items it needs add up to less than the forecast.
Step 4 · Send the invitation with a timebox and an agenda
The Scrum Guide caps sprint planning at eight hours for a one-month sprint and says it is usually shorter for shorter sprints. Many teams on two-week sprints book up to four hours and finish early when preparation was good. Book two hours to start with. Larkfield's calendar keeps its standing 09:30–12:30 planning slot on day 1, inside the four-hour cap, but the agenda below is planned for ninety minutes, because refinement on day 6 has already done the slow part. If the meeting finishes at 11:00, the rest of the slot goes back to the team.
Invite the whole Scrum team. The Guide allows the team to invite others for advice, so if an item depends on someone outside the team, ask them to join for that part only. Larkfield invites the clinic's reception lead for the first twenty minutes, because the appointment-system item changes how reception works.
Put the agenda in the invitation, following the three topics the Guide sets:
- Why is this sprint valuable? Agree the sprint goal. (20 minutes)
- What can be done this sprint? Developers choose items against the forecast. (30 minutes)
- How will the chosen work get done? Developers break items into tasks. (30 minutes)
- Close. Read the goal aloud and publish the sprint backlog. (10 minutes)
Attach the capacity sheet, the refined backlog and the proposed goal. Keep the pre-read to a single page or board link rather than a recorded video: some of the team may be reading it on a phone over mobile data, and a short page loads anywhere.
Check it worked
The invitation shows a fixed end time, the three topics with times, and links to the capacity sheet, the backlog and the proposed goal. Everyone in the Scrum team has accepted.
Step 5 · Agree the sprint goal first
Open with the proposed goal on the screen, not the backlog. The product owner reads it and explains in two or three sentences why it matters now.
For Larkfield, Ngozi explained that reception cannot trial online booking until bookings reach the appointment system, and the trial has to start in Sprint 3 to meet the release date.
Then ask the developers three questions:
- Is anything in the goal unclear? Achieng asked whether "on their phone" meant every phone or a test phone. The team settled on "on a phone", with the low-end Android work left as a separate item.
- Does it look achievable in the forecast? If the developers look doubtful, shrink the goal now, not after choosing items.
- Is there anything it leaves out that someone would expect? The reception lead asked about the privacy notice. Without it, no real patient can enter their details, so the team added "with the privacy notice in place" to the goal.
Larkfield's final goal:
A patient can book a free slot on a phone, with the privacy notice in place, and the booking appears in the clinic's appointment system with no chance of double booking.
The Guide says the sprint goal "must be finalized prior to the end of Sprint Planning". In practice, settle it before you choose items, then check at the end that it still fits.
Check it worked
The final goal is written at the top of the sprint page, in one sentence. Each developer has said out loud that they understand it and think it is achievable.
Step 6 · Let the developers choose what fits
Now open the backlog. The Guide puts selection with the developers, "through discussion with the Product Owner". The product owner explains items and answers questions; the developers decide how much they take.
Work down the ordered backlog. For each item, the developers ask two questions:
- Does this help meet the goal? If yes, it is a candidate.
- Does the running total still fit the forecast? Write the total next to the forecast as you go.
At Larkfield:
| Item | Estimate | For the goal? | Running total |
| --- | --- | --- | --- |
| Patient books a slot | 4 | Yes | 4 |
| Booking appears in the appointment system | 6 | Yes | 10 |
| Confirmation screen with reference | 1 | Yes | 11 |
| Privacy notice and consent wording | 1 | Yes | 12 |
| Works on low-end Android and with assistive technology | 3 | No, but next in order and fits | 15 |
| SMS confirmation | 2 | No; would take the total past 16 | not taken |
The goal needs 12 days. With 16 forecast, the developers took the low-end phone item too, because it was next in the product owner's order and fitted. They left the SMS confirmation out, because taking it would leave no room for surprises in the appointment-system work, which Dev thought was the riskiest item.
Two rules keep this honest:
- The product owner does not push extra items in. If Ngozi wants SMS this sprint, she asks the developers what would have to come out.
- Goal items come first. If the forecast is tight, drop items that are not for the goal before touching ones that are.
The team may refine items while choosing; the Guide allows this. If an item turns out bigger than its estimate, re-estimate it now and redo the running total.
Check it worked
The sprint backlog lists the chosen items with a total that is at or below the forecast on the capacity sheet. Every item needed for the goal is in, and the developers, not the product owner, made the last cut.
Step 7 · Plan how the work gets done
For each chosen item, the developers plan the work needed to finish it to the definition of done. The Guide notes this is "often done by decomposing Product Backlog items into smaller work items of one day or less" and that how they do it is "at the sole discretion of the Developers". The product owner stays to answer questions but does not assign tasks.
Larkfield broke "Booking appears in the appointment system" into tasks like these:
- Read the appointment system's booking interface documentation and confirm the fields it needs (half a day)
- Write the call that creates a booking, with a test against the supplier's sandbox (1 day)
- Lock a slot while a patient is booking so two people cannot take it (1 day)
- Handle the appointment system being unavailable: show the patient a clear message and keep their details for one retry (1 day)
- Test with reception using five fake patients (half a day)
While planning, the riskiest item often turns out bigger than expected. If that happens, go back to the previous step and adjust the selection, starting with items that are not for the goal. Larkfield's tasks for the appointment-system item added up to about the 6 days estimated, so nothing changed.
You do not need tasks for every item before the meeting ends. Plan the first few days in detail and leave later items with a rough outline; the team will plan them in daily stand-ups.
Check it worked
Every item needed for the goal has at least its first tasks written, each a day or less. Someone has picked up a task for the first morning of the sprint, by their own choice.
Step 8 · Close the meeting and check the goal from outside
Spend the last ten minutes on three things.
Read the goal and the sprint backlog aloud. The Guide defines the sprint backlog as the goal, the chosen items and the plan for delivering them. Read all three so nobody leaves with a different picture.
Agree what happens if the work turns out different. The goal is the commitment. If an item grows during the sprint, the developers talk to the product owner and renegotiate the scope without changing the goal. At Larkfield, the team agreed the low-end phone item is the first to move to Sprint 3 if the appointment-system work runs long.
Publish it. Put the goal at the top of the board, where the team sees it every day, and send it to stakeholders with the total available days and the forecast. Keep the per-person rows, with each person's leave and duty, inside the team.
Then do the test the goal is for. Send it to one person outside the team, with no other context, and ask them: "How would you know, on the last day, whether this was met?" Larkfield sent it to the clinic manager, who replied: "I'd book a slot on my own phone, see the privacy notice, and then ask reception to show me my booking in the system. And I'd try to book the same slot from a second phone and expect it to fail." That matches what the team meant, so the goal works.
If the reply is vague, or describes something different, rewrite the goal with the team the same day. It is better to find a goal that outsiders misread now than at the sprint review.
Check it worked
The goal is at the top of the board and in a message to stakeholders. Someone outside the team has replied with a concrete description of how they would check it, and that description matches what the team plans to show.
Next steps
You now have a sprint goal the team committed to, a sprint backlog the developers chose against a forecast with visible sums, and a capacity sheet you can reuse next sprint by changing the leave and duty columns.
- Keep the goal in view every day with a daily stand-up that stays short.
- If your estimates keep missing, try estimating with ranges instead of single numbers.
- Decide what the whole release must contain before planning its sprints with MoSCoW release scoping.
- Review how well the ratio and the goal worked in a retrospective that changes something.
Related tutorials
- Write user stories with clear acceptance criteriaYou will have five user stories for a clinic's reschedule feature, each checked against INVEST and carrying Given / When / Then acceptance criteria that a developer and a tester read the same way.
- Write tickets developers want to pick upYou will rewrite three vague backlog tickets into ones a developer can start without asking a question, and save the structure as a ticket template in your tracker.
- Write a weekly stakeholder update people readYou will have a reusable weekly update template and one finished update under 250 words, whose first two lines tell any reader whether they need to act.
Need this done for you?
Padding does this work for growing companies, from the first diagnosis to a system that keeps working.
Get new tutorials