Product and project management · Intermediate · 16 min

Make the case for paying down technical debt

By Padding · Updated 18 Nov 2026
Any document editor · November 2026

You will have a debt register linked to your roadmap and a one-page proposal that gives stakeholders two costed options for paying down technical debt and a recommendation.

On this page

"The booking code is a mess" is true at most companies, and it almost never wins time on a roadmap. Stakeholders hear a complaint with no price attached, and the next feature request has a price and a date. If you want time to fix the code, the case has to be made in the terms the people deciding already use: which plans it slows, what it costs now, what it costs to wait, and what you are asking for instead.

Ward Cunningham, who coined the term in 1992, described shipping code that is not quite right as going into debt: you move faster today, and every later change pays interest until you go back and fix it. The useful part of the metaphor for a product manager is the interest. Nobody funds a clean-up because the code is untidy. They fund it when the interest shows up on the roadmap.

The running example is Larkfield Clinic, a fictional community clinic moving to online booking and appointment reminders, with a small development team led by Daniel Mwangi, the tech lead. Its roadmap has two items in Now (an SMS reminder trial, and moving off a booking server whose support ends on 28 February 2027), and online booking and cancelling without a phone call in Next. The clinic's regional health board requires patients to be able to cancel without phoning by 1 July 2027. You will work with Daniel to turn his complaint into a one-page proposal the clinic manager and board can weigh. Use your own product and engineer if you have them.

Step 1 · Turn the complaint into named items

Book an hour with the tech lead. Bring the roadmap. The goal of the hour is a list of specific things that are wrong, each written so a non-engineer can follow it.

Ask these questions, in this order:

  1. Which part of the code do you dread changing, and why?
  2. What was the last change that took much longer than it should have? What made it slow?
  3. What has broken in the last three months, and was the cause in the code or somewhere else?
  4. If you had two clear weeks, what would you fix first?

Write each answer as one item: what is wrong, and what that does to change. "The slot code is a mess" becomes "the rules for which appointment slots are free are copied in three places, so every booking change has to be made three times and tested three times".

Daniel's list for Larkfield:

  • D1. Slot rules are copied in the reception screen, the SMS reminder script and the nightly report.
  • D2. No automated tests on slot allocation. Every change is checked by hand, and two double-bookings slipped through last quarter.
  • D3. Appointment dates are stored as text (03/12/2026) rather than as dates, so sorting and comparing them needs special handling everywhere.
  • D4. Reminder wording is written into the code in English, so changing a word or adding a language means a code change and a release.
  • D5. The booking page loads a large, old date-picker library that is slow on low-end Android phones and costs patients on prepaid data more than it should.

Keep bugs separate. A bug is something users see going wrong. Debt is something in the code that makes change slow or risky. The double-bookings are bugs; the missing tests (D2) are the debt that let them through. Bugs go on the backlog as usual. Only the debt goes on this list.

Check it worked

You have three to eight items, each one sentence long, and each says what it does to future work, not only what is wrong. Read one aloud to someone outside the team; they can repeat back why it matters without asking what a word means.

Step 2 · Start a debt register and record the kind of each item

A register is a table that keeps the list alive after this proposal. Create it as a table in your document or as a spreadsheet. Use these columns:

Text
ID | Debt | Where | Kind | Why it happened | Slows (roadmap) | Evidence | Cost of waiting | Fix estimate | Owner | Status | Last reviewed

Fill in ID, Debt and Where now. The other columns come in the next steps.

The Kind column records how the debt arrived, because that changes the conversation:

  • Deliberate: the team knew it was cutting a corner and chose to, usually for a deadline. This is often a sound choice. The record should say what the corner was and when the team meant to come back.
  • Accidental: nobody chose it. The team learned a better design later, the product grew in a direction nobody planned, or a library aged while the code stood still.

Martin Fowler adds a second split: prudent or reckless. In his examples, prudent deliberate debt sounds like "We must ship now and deal with consequences"; reckless deliberate debt sounds like "We don't have time for design". You do not need all four boxes in the register, but if an item was reckless, say so in the Why column. Stakeholders trust a register more when it admits the team's own part.

For Larkfield, D2 was deliberate: tests were skipped to launch the reception screen before a 2025 inspection. D1 and D3 were accidental, from features added one at a time. D5 is accidental: the library was fine when chosen and has not been updated since.

Check it worked

Your register has every item from the first step in its own row, with a Kind of deliberate or accidental, and a one-line Why. For each deliberate item, the Why names the deadline or reason the corner was cut.

Step 3 · Connect each item to the roadmap

This is the step that turns a code problem into a product problem. Go through the roadmap with the tech lead, item by item, and ask: "Does this work touch any of the debt? If it does, how much slower or riskier is it because of it?"

Write the answer in the Slows column. Use roadmap item names, exactly as the roadmap writes them, so a reader can find them.

For Larkfield:

  • D1 (copied slot rules) slows online booking (Next) and cancelling without phoning (Next). Both change slot rules, so both would need the change made in three places, or a fourth copy written.
  • D2 (no tests) slows the same two items and adds risk to both, because every slot change is checked by hand.
  • D3 (dates as text) touches the server move (Now). Daniel says the cheapest moment to fix it is during the move, when the data is copied anyway.
  • D4 (English wording in code) slows reminders in other languages (Later).
  • D5 (old date picker) slows online booking (Next), which reuses the booking page.

If an item slows nothing on the roadmap, say so in the register. It may still be worth fixing, but it is not part of this proposal. Make the case for debt that sits in the path of work people already want.

Check it worked

Every row in the register either names at least one roadmap item in Slows, or says "nothing on the current roadmap". At least one item names something in Now or Next.

Step 4 · Count what the debt costs today

Interest you can point to is more convincing than interest you predict. Collect what the debt has already cost, from records that exist, over a fixed recent period. Three months is usually enough.

Look in:

  • Incident notes or support tickets: problems traced to the debt, with time to fix and anyone else affected (reception staff, patients).
  • Finished tickets: changes that took much longer than estimated. Ask the tech lead which part of the overrun was the debt.
  • The tech lead's memory: fine to use, but label it as an estimate.

Write each figure in the Evidence column with its source in brackets, the same way you would for any number a stakeholder might question.

For Larkfield, over August to October 2026:

  • D1: the reminder trial change was estimated at 4 days and took 9, because the slot rules had to be changed and checked in three places (ticket history; Daniel's split of the overrun).
  • D2: two double-bookings reached patients. Each took a developer about a day and a half to trace and fix, and reception spent an afternoon phoning the patients affected (incident notes).
  • D5: the booking page is about four times heavier than the rest of the site (Daniel measured it in the browser); no complaints logged, but the clinic's patients mostly book from phones.

Add the time up and keep it in days, not money. Stakeholders can turn days into money if they want to; a figure in their own currency that you invented invites an argument you do not need. For Larkfield, D1 and D2 cost about 8 developer days in three months, roughly 13% of one developer's time, plus two afternoons of reception time.

Check it worked

Each register row on the proposal has at least one Evidence figure with a source in brackets, and anything that is an estimate says so. You can state one sentence that begins "In the last three months, this debt cost us…" and ends with a number.

Step 5 · Work out the cost of waiting

Today's cost is the interest already paid. The cost of waiting is what happens to the roadmap if nothing changes. Ask the tech lead to estimate the affected roadmap items twice: as things stand, and after the debt is paid. Use ranges, not single numbers; a single number sounds more certain than anyone is.

For Larkfield, Daniel's estimates for the two Next items:

Text
                                  As things stand   After fixing D1 and D2
Online booking                    7 to 9 weeks      4 to 5 weeks
Cancel without phoning            3 to 4 weeks      1 to 2 weeks
Fix D1 and D2 first               –                 3 weeks
Total, from the start of March    10 to 13 weeks    8 to 10 weeks

The order matters, so write it down: cancelling reuses the online booking page and the patient login that online booking adds, so it is built second. That is why the fixed date depends on how long online booking takes, even though cancelling is the smaller job.

Then look for anything that makes waiting worse over time:

  • Fixed dates. Larkfield must let patients cancel without phoning by 1 July 2027. Starting on Monday 1 March, the work as things stand ends between 7 and 28 May, leaving five to eight weeks of slack. After the clean-up, it ends between 23 April and 7 May, leaving eight to ten weeks.
  • Growth. Online booking would add a fourth copy of the slot rules. Debt that grows each time you build is the strongest case for paying it early.
  • Risk. Double-bookings continue at about two a quarter while D2 stands, and online booking adds more ways to book.

Fill in the Cost of waiting and Fix estimate columns for each item on the proposal.

Check it worked

You have a before-and-after estimate, as ranges, for at least one roadmap item, and the totals include the time the fix itself takes. Each item on the proposal has a Cost of waiting entry that names a date, a growth effect or a risk.

Step 6 · Shape the options

There are three usual ways to deal with debt. Work through all three with the tech lead before you pick which to put forward.

  • A fixed share of each sprint. A set part of every sprint, often one day in five, goes to items on the register. Steady and easy to plan around, but slow to finish any one item, and it competes with every deadline.
  • A focused clean-up. A block of time, usually one to three weeks, spent on named items before the work they slow. Fast, and the payback is easy to show, but nothing else moves in that block.
  • Accept it. Decide not to pay a piece of debt now, and write down why and what you will watch. Right for debt that slows nothing important, or for products near the end of their life.

You can mix them. Larkfield's D3 is handled by neither: Daniel fixes the date format during the server move, which is in Now and already planned. Write that in the register as "fold into server move" so nobody is surprised later.

For each option, write three lines: what it costs, which roadmap items it speeds up, and what it puts at risk. For Larkfield:

  • Focused clean-up, three weeks at the start of March, for D1 and D2. Costs three weeks before online booking starts. Speeds up online booking and cancelling without phoning; the total for both drops from 10 to 13 weeks to 8 to 10. Risk: nothing visible ships in those three weeks.
  • One day in five from March, for D1, D2 and then D4. Costs a fifth of each sprint, so both Next items take longer: online booking about 9 to 11 weeks instead of 7 to 9, and cancelling 4 to 5 instead of 3 to 4, a total of 13 to 16 weeks that ends between late May and mid June. Fixing D1 and D2 (15 days) at one day a week is not finished until around mid June, too late to help either item. Speeds up mainly reminders in other languages (Later). Risk: the 1 July deadline has the least slack of any option, two to five weeks.
  • Accept D1 and D2. Costs nothing now. Online booking starts on time in March. Risk: the 1 July cancellation deadline has five to eight weeks of slack rather than eight to ten, online booking adds a fourth copy of the slot rules, and double-bookings continue.

Starting a fixed share in December would slow the server move, which has its own fixed date, so Larkfield's options all start in March. Check your own options against your own fixed dates the same way.

Pick the two options that are both realistic for your team. Keep the third in the register and mention it in one line in the proposal, so readers know it was considered.

Check it worked

You have written cost, speeds-up and risk lines for each option, and every option except "accept" names at least one roadmap item it speeds up. You have chosen two options for the proposal and can say in one sentence why the third was dropped.

Step 7 · Write the one-page proposal

The proposal is for people who will not read the register. Keep it to one page. Use these headings:

  1. The ask, in two lines. What you want and when. "Three weeks in March for the booking clean-up, before online booking starts."
  2. What is wrong, in plain words. Two or three sentences, no code terms. Name only the debt the proposal covers.
  3. What it costs now. The figures from your Evidence column, with sources.
  4. What waiting costs. The before-and-after table and any fixed date it affects.
  5. Option 1 and Option 2. Each with its cost, the roadmap items it speeds up, and its risk.
  6. Recommendation. Which option, and the one reason that decides it.
  7. How we will know it worked. One or two things to check afterwards.
  8. Not included. The option you dropped and any debt you are accepting, one line each.

For Larkfield, the recommendation reads: "We recommend Option 1, the three-week clean-up in March. It costs three weeks, saves two to three weeks across online booking and cancelling without phoning, and gives the 1 July deadline eight to ten weeks of slack instead of five to eight. We will know it worked if online booking ships within its 4 to 5 week estimate and no double-bookings reach patients in the quarter after."

Write the "how we will know" line with care. It is the promise stakeholders will hold you to, and it is how you earn the next request.

If the people reading work in more than one language, as many clinic boards and staff across Africa do, have someone read the plain-words section in the language they are most comfortable in. Debt proposals fail as often on jargon as on numbers.

Check it worked

Your proposal fits on one page and has all eight headings. Each of the two options names at least one roadmap item it speeds up, using the item's name as the roadmap writes it. The recommendation says which option and gives one deciding reason.

Step 8 · Review it, decide, and keep the register going

Send the draft to the tech lead first and ask them to check every estimate and every sentence about the code. Then read it with one stakeholder who will help decide, before the meeting. Ask them which number they doubt most, and strengthen that one.

After the decision, update the register:

  • Set Status for each item: scheduled (with the sprint), folded into other work, accepted, or done.
  • For accepted debt, write what would make you raise it again, such as "a third double-booking in a quarter" or "a decision to add another language".
  • Add a Last reviewed date, and put a recurring review on the calendar. Once a quarter, alongside the roadmap review, is enough for most teams.

Report progress in your usual stakeholder update. Cleaned-up debt is invisible to users, so say when it lands and what it changed: "The slot clean-up finished on 20 March; online booking started on 23 March against a 4 to 5 week estimate."

Check it worked

The register shows a Status for every item and a Last reviewed date, and each accepted item has a written trigger for raising it again. A recurring register review is on the calendar, and the tech lead has confirmed the estimates in the proposal.

Next steps